Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 

Auckland Region Rail Upgrade Project Plan details

Auckland Region Rail Upgrade Project

Plan details

Start and completion dates

The Auckland Region Rail Upgrade Project begins in 2002. Infrastructure improvements are planned to be fully completed by January 2006 and the target service levels (of 10-minute frequencies throughout the network at peak times) are to be running by December 2006.

Project partners

The project has two partners: The Auckland Regional Council (ARC) manages rolling stock and service procurement. Auckland Regional Transport Network Ltd (ARTNL) manages infrastructural upgrades and is the rail network manager.

Infrastructure upgrades

ARTNL plans to upgrade the infrastructure in two phases.

Phase A - completion by July 2003

This phase includes footbridge safety improvements, improvements to existing drainage, minor track and signalling changes at New Lynn, fencing and road and pedestrian level crossings improvements.

Sub-total: Infrastructure $7.9 million

Initially three stations in Manukau, Waitakere and Papakura (one in each) will be upgraded. Minor station amenity and safety upgrades (CCTV, remote monitoring, lighting, painting and platform surface improvements) will be carried out at all stations except Britomart.

Sub-total: Stations $3.1 million

TOTAL INFRASTRUCTURE CAPITAL COST PHASE A: $11 million

Phase B - completion by January 2006

The components of Stage B are:

- Double tracking from Kingsland to Glen Eden on the Western line, including bridge and structure additions and modifications

- Completion of improvements to level crossings, drainage and fencing over whole system

- Land acquisition (corridor)

- Infrastructure service level improvements

- Double tracking of the Western line from Boston Road to Kingsland, and from Glen Eden to Swanson, including bridge and structure additions and modifications

- Signalling system replacement on the Western line including the Newmarket area

- Signalling system - fibre optic cable along all corridors

- Westfield-Otahuhu track changes, platform re-construction, at-grade separation and signalling changes

- Train storage and light maintenance facility (Swanson, Parnell)

- Contract supervision, consents, etc.

Sub-total: Track infrastructure $111.5 million

Station upgrading and park & ride including land acquisition: All existing station buildings, platforms and facilities and park and ride facilities will be upgraded to appropriate levels.

Sub-total: Stations $68.5 million

Manukau Rail Link $31 million (exclusive of enabling works)

TOTAL CAPITAL COST STAGE B $211 million

TOTAL COST - INFRASTRUCTURE $222 million

Rolling stock improvements

The ARC will manage the refurbishment of existing rolling stock (trains) and procure additional rolling stock.

1. Purchase and refurbishment of existing trains

ARC will commission refurbishment of existing 10 ADL units to meet immediate service level requirements. The aim is to complete refurbishment by June 2003 along with a minor upgrade of the 9 ADK units.

Cost $3 million to purchase existing trains, $8 million refurbishment

Timing 2002 - 2003

2. Procurement of interim rolling stock

The ARC will source interim rolling stock to meet service level requirements and provide operational spares between 2002 and 2007. Exact fleet numbers will be dependent on actual delivery date of new rolling stock.

Cost $10 million

Timing 2002 - 2007

3. Purchase of new trains

The ARC has estimated costs of purchasing 25 new DMU units to be $5.8m per 2-car unit. The ARC will run a competitive tender process to select a supplier (designer and manufacturer) of long-term rolling stock. This is to ensure that we choose the best option for Auckland for the long term.

Cost $145 million

Timing 2003 - 2006

TOTAL COST ROLLING STOCK $166 million

TOTAL ESTIMATED COST OF RAIL PROJECT $388 million


© Scoop Media

 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

Gordon Campbell: On The Tax Working Group’s Road Map

Trying to analyse the interim report on the Tax Working Group (TWG) is like trying to review an entire All Blacks game, but at the half- time mark.

With so much still to be finalised, Sir Michael Cullen and his colleagues are going to need all the All Blacks’ fabled finishing skills to get a coherent, fiscally neutral package together by the February 2019 deadline. More>>

 

Meth Testing Report: Housing NZ "To Right Wrong"

Phil Twyford “Housing NZ acknowledges that around 800 tenants suffered by either losing their tenancies, losing their possessions, being suspended from the public housing waiting list, negative effects on their credit ratings or, in the worst cases, being made homeless.” More>>

ALSO:

No Reshuffle: Meka Whaitiri Removed As A Minister

Meka Whaitiri will be removed as a Minister with immediate effect... The decision was made after receiving a report into an incident that occurred on 27 August in Gisborne, involving Meka Whaitiri and one of her staff. More>>

ALSO:

Pay Equity Bill: Making History For Women’s Pay

The Equal Pay Amendment Bill, introduced to the House today, will make it easier for workers to make a pay equity claim , using a more simple and accessible process within New Zealand’s existing bargaining framework. More>>

ALSO:

Suffrage 125: NZ A Trailblazer For Women

“We acknowledge the work of Kate Sheppard, Meri Te Tai Mangakāhia, and all of the suffragists who tirelessly campaigned for the vote… Today we also need to ask each other: how we can continue to make our country a fairer and better place to continue the legacy of the suffragists.” More>>

ALSO:

Asylum: Refugee Quota Increasing To 1500

“The quota increase will take place from July 2020. In the meantime, we will work to increase the number and spread of refugee resettlement and support services. We need to make sure we’re prepared for this change in policy.” More>>

ALSO:

 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels