Update on Paremata to Plimmerton Upgrade

Monday 17 May 2004

Update on Paremata to Plimmerton Upgrade

While work on State Highway 1 Paremata to Plimmerton Upgrade is continuing to progress well, it is now likely to be completed in June next year - not March as originally expected.

The main reasons for the delay in completing the project are: Wet weather – summer is traditionally the road-building season Utility clashes – power, water and gas services are not where they were thought to be Property modifications – more work was required on some properties than expected

Project manager Catherine Worsley explains: “With constricted urban sites, the work can only be carried out in a particular sequence.

“For instance, along Mana Esplanade we first have to modify the front of 56 properties, prior to relocating services and before completing the kerb and channel. Then we can get on to building the footpath and finally the road.

“While we can estimate how long all of this will take, it is more difficult to allow for what we don’t know about.

“An example of this is when we were installing the storm water pipes along Mana Esplanade, we encountered existing power cables laid at various depths which were different to the underground service maps.

“These had to be lowered before we could continue with the storm water installation. In order to keep SH1 open while we carried out the work we had to use several purpose-built plates so that vehicles could drive over the trench in the road.

“Unfortunately lots of small delays like these accumulate and can result a much bigger delay at the end.”

Ms Worsley added that although the new completion date is now June 2005, there are still some challenges in the future that will have to be met to achieve that date. These include:

More wet weather than anticipated Further utility clashes Unforeseen events such as any archaeological finds Settlement of the western side of SH1, near Plimmerton Weigh Station, takes longer than expected Extra maintenance work on the existing highway (at the northern end of the site) is required

She said: “We hope that none of these things will happen, but obviously we can’t guarantee that any of them, or indeed all of them, won’t occur.

“In respect to traffic delays, we will endeavour to provide as much advance warning as we can of any activities which may have an impact on travel times for motorists.”

Motorists can also help reduce delays - especially if they know of a significant project activity, or are aware of an event that will result in heavy traffic in to, or out of, Wellington.

Drivers may want to make alternative arrangements such as taking the train, car-pooling (less vehicles equals shorter queues) and travelling outside of peak traffic hours.

Transit also urges motorists to follow all traffic management instructions, avoid rubber-necking at scheduled works and being courteous to other drivers by letting them merge. Avoiding the temptation to use “short-cuts”, such as Airlie Road, will also help traffic flow.

The good news in regards to the upgrade is that some major milestones have been met in the last few months. These include:

The ground opposite Plimmerton Weigh Station is being prepared for road construction Acoustic mitigation of 50 properties is all but complete The new kerb and channelling along Mana Esplanade has almost reached Pascoe Avenue Goat Point retaining wall is nearly half way to completion.

Widening the northern end of the site, between Plimmerton weigh station and James Street, to four lanes is still on target to meet its December deadline.

In July the duplicate Paremata Bridge will open to traffic - with a view to having both bridges fully operational by the end of the year. During the five months in between, traffic will be diverted to the new bridge (or a combination of the two) while the approaches to the existing one are re-built, the bus bay constructed and the barriers and retaining walls between the new and existing bridges are installed.

Other milestones will be posted on the Transit New Zealand website which can be viewed at www.transit.govt.nz/projects.

ENDS

© Scoop Media

 
 
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 

Ruataniwha: DOC, Hawke's Bay Council Developer Take Supreme Court Appeal

The Department of Conservation and Hawke's Bay Regional Investment Company (HBRIC) are appealing to the Supreme Court over a conservation land swap which the Court of Appeal halted. More>>

ALSO:

With NZ's Marama Davidson: Women’s Flotilla Leaves Sicily – Heading For Gaza

Women representing 13 countries spanning five continents began their journey yesterday on Zaytouna-Oliva to the shores of Gaza, which has been under blockade since 2007. On board are a Nobel Peace Laureate, three parliamentarians, a decorated US diplomat, journalists, an Olympic athlete, and a physician. A list of the women with their background can be found here. More>>

Gordon Campbell: On The Key Style Of Crisis Management

At Monday’s post Cabinet press conference Key was in his finest wide- eyed “Problem? What problem?” mode. No, there wasn’t really a problem that top MPI officials had been at odds with each other over the meaning of the fisheries policy and how that policy should be pursued... More>>

ALSO:

Mt Roskill: Greens Will Not Stand In Likely Post-Goff By-Election

“The Green Party’s priority is changing the Government in 2017, and as part of that we’ve decided that we won’t stand a candidate in the probable Mt Roskill by-election... This decision shows the Memorandum of Understanding between Labour and the Green Party is working." More>>

ALSO:

Wellington: Predator Free Capital Plan

Wellington City Council (WCC), the Greater Wellington Regional Council (GWRC) and NEXT Foundation, today announced a joint collaboration to make Wellington the first Predator Free capital city in the world. More>>

ALSO:

Gordon Campbell: On Judith Collins’ Efforts At Self Correction

Thousands of prisoners currently in prison may be entitled to an earlier release than expected – and compensation – because Corrections has incorrectly calculated their term of imprisonment. Unless of course, the government buries its mistakes by changing the law and retro-actively getting itself off the hook… More>>

ALSO:

More Justice & Corrections

Sector Opposes Bill: Local Government Bill Timeframe Extended

The Minister of Local Government Peseta Sam Lotu-Iiga has asked the Select Committee to extend the report back date for the Local Government Act 2002 Amendment Bill (No 2). More>>

ALSO:

Get More From Scoop

 

LATEST HEADLINES

 
 
 
 
 
 
 
 
 
Regional
Search Scoop  
 
 
Powered by Vodafone
NZ independent news