Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search


Ferrymead Bridge replacement progressing well

Wednesday 9 April 2013

Ferrymead Bridge replacement progressing well

The Ferrymead Bridge replacement project is on schedule with the demolition of the existing bridge expected to be complete before the end of April 2013.

With the ‘nibbler’ cranes completing the final demolition of the existing bridge, the next part of the work is the pile removal. This is a delicate operation, as the removal process takes place under water.

Once the older piles are removed, preparation work can start to allow for heavy machinery to move into place and begin the piling for the base of the new Ferrymead Bridge. This is called the staging process whereby land ‘fingers’ are constructed in the water, for the heavy machinery to work from during the piling construction.

Unit manager of Transport and Greenspace John Mackie says, “It’s great news that the work on the Ferrymead Bridge replacement is on schedule and progressing as planned. We know how important this transport artery is to all the residents and businesses. With 30,000 vehicles using this route daily, it is reassuring for all to know that this project is on target.”

The work on demolishing the existing bridge began in February 2013, and the temporary bridges were installed in late January 2013. Completion of the new bridge is likely to be by mid 2015, but timeframes may have to be adapted if unexpected ground conditions for piling are encountered.
The piling process for the new bridge will take about 15 months and start as soon as the existing bridge is demolished.

What’s coming up in the next few months:

• Pile removal – expected to be completed by the end of April 2013.
• Bridge foundation removal and backfilling – planned for completion at end of April 2013.
• Staging installation – planned to start at end of April 2013 and is dependant on the completion of the pile removal activity above. Expecting to have this complete by the middle of May 2013.
• Pile gate construction – planned to begin as soon as the staging ‘fingers’ have been constructed, which would be at the end of May 2013.
• Pile construction – the first pier pile work should start by the middle of June 2013.

Please note that the activities listed above are dependant on the completion of the demolition works and subject to weather.

For more information on the Ferrymead Bridge project, please visit the Christchurch City Council website. There is also a list of frequently asked questions available on the website to assist with any queries you may have.

To view please visit http://www.ccc.govt.nz/ferrymead


© Scoop Media

Parliament Headlines | Politics Headlines | Regional Headlines



Labour: Little Announces New Shadow Cabinet

“Labour had an impressive intake of fresh faces after last year’s election and newest MPs have now had a year to show what they’re made of. This reshuffle rewards hard work and continues my drive to renew our Caucus line up." More>>


Whaling: NZ Deeply Disappointed By Japan's Decision

“New Zealand is strongly opposed to whaling in the Southern Ocean. We call on Japan to take heed of the 2014 International Court of Justice decision and international scientific advice concerning their whaling activities.” More>>


Relevant Consents Gained: Government Unveils RMA Reform Package

The government has formally hauled down the flag on its attempts to alter the balance of environmental and economic priorities in the Resource Management Act, unveiling a 180-page Resource Legislation Amendment Bill containing reforms that have been largely endorsed by most political parties. More>>


Closing Schools And Such: Interim Redcliffs Decision Announced

“While the school’s board has argued that circumstances that could give rise to potential disruption are extremely unlikely, advice from technical experts has shown these concerns cannot be ruled out." More>>


Jane Kelsey: High Court Can’t Make Groser Provide TPPA Information Faster

‘This week we went back to court to challenge Trade Minister Groser’s stalling tactics over the release of information on the Trans-Pacific Partnership Agreement negotiations, following a High Court order that he reconsider the Official Information Act request I made last January’, said University of Auckland law professor Jane Kelsey, first applicant in the case. More>>

Werewolf 58: No Climate For Change

The last time the global community tried to take collective action on climate change the world’s leaders finally came to agree that every not-too-onerous effort should be made to hold global warming to 2°C above the pre-industrial average. At Paris, all 150 participant countries nations will have put forward their pledges... On the information available, New Zealand's is the second weakest contribution of any nation in the developed world. More>>


Lambton Quay Shutdown: Object Was Made To Look Like Bomb

Police cordoned off part of Lambton Quay Wednesday afternoon, saying that a suspicious package had been found. Buildings were evacuated and buses were detoured. The army’s explosive ordnance disposal unit was brought to the Quay. More>>


Public Sector Still Shrinking: Record Low Number Of 'Backroom Bureaucrats'

Ongoing restraint in the public sector and a focus on better frontline services has seen a further reduction in the number of core Government employees, State Services Minister Paula Bennett says. More>>


Disobeying The Law: Police Censorship Of Crime Research “An Outrage”

The Green Party is calling on Police Minister Michael Woodhouse to ensure Police scrap controversial contracts that place onerous restrictions on academic researchers’ access to Police data, the Green Party says. More>>


Get More From Scoop



Search Scoop  
Powered by Vodafone
NZ independent news