Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 

Ferrymead Bridge replacement progressing well


Wednesday 9 April 2013

Ferrymead Bridge replacement progressing well


The Ferrymead Bridge replacement project is on schedule with the demolition of the existing bridge expected to be complete before the end of April 2013.

With the ‘nibbler’ cranes completing the final demolition of the existing bridge, the next part of the work is the pile removal. This is a delicate operation, as the removal process takes place under water.

Once the older piles are removed, preparation work can start to allow for heavy machinery to move into place and begin the piling for the base of the new Ferrymead Bridge. This is called the staging process whereby land ‘fingers’ are constructed in the water, for the heavy machinery to work from during the piling construction.

Unit manager of Transport and Greenspace John Mackie says, “It’s great news that the work on the Ferrymead Bridge replacement is on schedule and progressing as planned. We know how important this transport artery is to all the residents and businesses. With 30,000 vehicles using this route daily, it is reassuring for all to know that this project is on target.”

The work on demolishing the existing bridge began in February 2013, and the temporary bridges were installed in late January 2013. Completion of the new bridge is likely to be by mid 2015, but timeframes may have to be adapted if unexpected ground conditions for piling are encountered.
The piling process for the new bridge will take about 15 months and start as soon as the existing bridge is demolished.

What’s coming up in the next few months:

• Pile removal – expected to be completed by the end of April 2013.
• Bridge foundation removal and backfilling – planned for completion at end of April 2013.
• Staging installation – planned to start at end of April 2013 and is dependant on the completion of the pile removal activity above. Expecting to have this complete by the middle of May 2013.
• Pile gate construction – planned to begin as soon as the staging ‘fingers’ have been constructed, which would be at the end of May 2013.
• Pile construction – the first pier pile work should start by the middle of June 2013.

Please note that the activities listed above are dependant on the completion of the demolition works and subject to weather.

For more information on the Ferrymead Bridge project, please visit the Christchurch City Council website. There is also a list of frequently asked questions available on the website to assist with any queries you may have.

To view please visit http://www.ccc.govt.nz/ferrymead


ENDS

© Scoop Media

 
 
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

Gordon Campbell: On The Fallout From The Barclay Tape

This is hardly a case of cleaning out your desk and being turfed out onto the pavement.

As others have pointed out, the disgraced Clutha-Southland MP will remain on the public payroll for three months until the election, and for three months afterwards. More>>

 

Ombudsman: Canterbury Schools Reorganisation Mishandled

An investigation into the Canterbury schools reorganisation after the February 2011 earthquakes has found significant gaps and flaws in the Ministry’s engagement and communications with schools and communities. More>>

ALSO:

Law Commission: Contempt Report "Protects Right To Fair Trial"

The proposed Act limits what news media representatives and bloggers can report on court proceedings, but it also makes clearer than the current law where the line is between contempt and freedom of expression. More>>

ALSO:

Gordon Campbell: On Our Refugee Intake (And Uber’s Woes)

On figures released this week, there are currently 65.6 million people worldwide who have been displaced from their homes by war, famine or other external causes… More>>

ALSO:

IGIS Report: GCSB Support For Groser WTO Bid Not Illegal

“The inquiry has found that the GCSB did not act unlawfully or improperly in providing assistance to the New Zealand government campaign”, Ms Gwyn said. More>>

ALSO:

PM's Press Conference: Pike And Houses

There were questions on Pike River mine re-entry after new video from inside the drift was released over the weekend. English maintained a human effort would not be feasible irrespective of any future coalition demands from NZ First. He said the government would continue to work with families on non-manned re-entry. More>>

ALSO:

Flogging A Dead Horse: NZ First Seeks New s59 Referendum

10 years on from the so called “anti-smacking” law - NZ First calls for a binding referendum. NZ First MP Tracey Martin told TVNZ’s Q+A programme that the law change has had a “chilling effect” on NZ parents including herself. More>>

ALSO:

Always Interesting: Internet Party Has New Leader

The Internet Party has a new leader: Suzie Dawson... She currently resides in Moscow, Russia, where she has applied for temporary asylum due to severe persecution she reports being subjected to by those whose corruption she worked to expose.More>>

 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured InfoPages

Opening the Election
 
 
 
  • PublicAddress
  • Pundit
  • Kiwiblog