Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search


Ferrymead Bridge replacement progressing well

Wednesday 9 April 2013

Ferrymead Bridge replacement progressing well

The Ferrymead Bridge replacement project is on schedule with the demolition of the existing bridge expected to be complete before the end of April 2013.

With the ‘nibbler’ cranes completing the final demolition of the existing bridge, the next part of the work is the pile removal. This is a delicate operation, as the removal process takes place under water.

Once the older piles are removed, preparation work can start to allow for heavy machinery to move into place and begin the piling for the base of the new Ferrymead Bridge. This is called the staging process whereby land ‘fingers’ are constructed in the water, for the heavy machinery to work from during the piling construction.

Unit manager of Transport and Greenspace John Mackie says, “It’s great news that the work on the Ferrymead Bridge replacement is on schedule and progressing as planned. We know how important this transport artery is to all the residents and businesses. With 30,000 vehicles using this route daily, it is reassuring for all to know that this project is on target.”

The work on demolishing the existing bridge began in February 2013, and the temporary bridges were installed in late January 2013. Completion of the new bridge is likely to be by mid 2015, but timeframes may have to be adapted if unexpected ground conditions for piling are encountered.
The piling process for the new bridge will take about 15 months and start as soon as the existing bridge is demolished.

What’s coming up in the next few months:

• Pile removal – expected to be completed by the end of April 2013.
• Bridge foundation removal and backfilling – planned for completion at end of April 2013.
• Staging installation – planned to start at end of April 2013 and is dependant on the completion of the pile removal activity above. Expecting to have this complete by the middle of May 2013.
• Pile gate construction – planned to begin as soon as the staging ‘fingers’ have been constructed, which would be at the end of May 2013.
• Pile construction – the first pier pile work should start by the middle of June 2013.

Please note that the activities listed above are dependant on the completion of the demolition works and subject to weather.

For more information on the Ferrymead Bridge project, please visit the Christchurch City Council website. There is also a list of frequently asked questions available on the website to assist with any queries you may have.

To view please visit http://www.ccc.govt.nz/ferrymead


© Scoop Media

Parliament Headlines | Politics Headlines | Regional Headlines



1080 Threat: Police Arrest 60 Year Old Auckland Man

New Zealand Police have arrested a 60-year-old Auckland businessman in relation to the criminal blackmail threat to poison infant formula with 1080, made public in March this year. More>>


Canterbury Transition Bill First Reading: Government Hiding From ECan Submissions

The Government has radically reduced the amount of time for public submissions on their controversial ECan bill, says Labour’s Environment spokesperson Megan Woods... “Their shortened timeline could mean that instead of the usual six weeks, Cantabrians get just one week to submit their views on the bill." More>>


Gordon Campbell: On Our Apparent Inability To Stand Up To Australia

Alas, and only days before the first meeting between our Prime Minister John Key and the new Australian leader Malcolm Turnbull, this country is showing no sign of standing up for itself. Quite the reverse. We seem to be rolling over, and making gestures of appeasement. More>>


Health Not-So-Many Benefits: Auditor-General On Scrapped Cost-Saving Plan

The Auditor-General decided to look into the costs and benefits of HBL’s work in the health sector and, where possible, identify lessons... We found that several factors contributed to the difficulties that befell HBL and, in particular, the Finance, Procurement and Supply Chain (FPSC) programme. More>>


Wikileaks: TPP Intellectual Property Rights Chapter Released

“If TPP is ratified, people in the Pacific-Rim countries would have to live by the rules in this leaked text,” said Peter Maybarduk, Public Citizen’s Global Access to Medicines Program Director. “The new monopoly rights for big pharmaceutical firms would compromise access to medicines in TPP countries. The TPP would cost lives.” More>>


Redundancies: 120 Laws To Be Repealed

The Statutes Repeal Bill will remove 120 pieces of superfluous legislation, and parts of eight other acts. It is being consulted on before it is introduced to Parliament. “The proposed Bill would reduce the total number of public Acts in force by more than 10%,” Mr Joyce says. More>>


Gordon Campbell: On John Key’s Trip To Iraq

In the embedded press coverage on this trip, the absence so far of any evaluation of the wider context of what New Zealand thinks it is doing at Camp Taji has been striking. More>>


Labour: Parata Puts Brakes On Charter School Appraisal

“When the Ministry of Education recommended they compare the achievements of children at charter schools to those of their counterparts at state schools, the documents show Hekia Parata specifically prohibited them from doing so." More>>


Bad Day For Universities: Gun, Bomb Threats On Three Campuses

Dunedin Police are continuing their investigation into the threat made against the University of Otago. Staff are following a number of lines of inquiry, and police are working to verify the authenticity and source of the post. More>>


Get More From Scoop



Search Scoop  
Powered by Vodafone
NZ independent news