Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 


Ferrymead Bridge replacement progressing well


Wednesday 9 April 2013

Ferrymead Bridge replacement progressing well


The Ferrymead Bridge replacement project is on schedule with the demolition of the existing bridge expected to be complete before the end of April 2013.

With the ‘nibbler’ cranes completing the final demolition of the existing bridge, the next part of the work is the pile removal. This is a delicate operation, as the removal process takes place under water.

Once the older piles are removed, preparation work can start to allow for heavy machinery to move into place and begin the piling for the base of the new Ferrymead Bridge. This is called the staging process whereby land ‘fingers’ are constructed in the water, for the heavy machinery to work from during the piling construction.

Unit manager of Transport and Greenspace John Mackie says, “It’s great news that the work on the Ferrymead Bridge replacement is on schedule and progressing as planned. We know how important this transport artery is to all the residents and businesses. With 30,000 vehicles using this route daily, it is reassuring for all to know that this project is on target.”

The work on demolishing the existing bridge began in February 2013, and the temporary bridges were installed in late January 2013. Completion of the new bridge is likely to be by mid 2015, but timeframes may have to be adapted if unexpected ground conditions for piling are encountered.
The piling process for the new bridge will take about 15 months and start as soon as the existing bridge is demolished.

What’s coming up in the next few months:

• Pile removal – expected to be completed by the end of April 2013.
• Bridge foundation removal and backfilling – planned for completion at end of April 2013.
• Staging installation – planned to start at end of April 2013 and is dependant on the completion of the pile removal activity above. Expecting to have this complete by the middle of May 2013.
• Pile gate construction – planned to begin as soon as the staging ‘fingers’ have been constructed, which would be at the end of May 2013.
• Pile construction – the first pier pile work should start by the middle of June 2013.

Please note that the activities listed above are dependant on the completion of the demolition works and subject to weather.

For more information on the Ferrymead Bridge project, please visit the Christchurch City Council website. There is also a list of frequently asked questions available on the website to assist with any queries you may have.

To view please visit http://www.ccc.govt.nz/ferrymead


ENDS

© Scoop Media

 
 
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 

PARLIAMENT TODAY:

Labour: New Figures Show Speculators Rampant

New figures released by the Reserve Bank show there’s been an explosion in mortgage lending with most of the growth going to property investors, Labour’s Housing spokesperson Phil Twyford says. More>>

ALSO:

False Official Information Response: English's Apology Accepted

Finance Minister Bill English is being thanked for his apology to New Zealand First Leader and Member of Parliament for Northland Rt Hon Winston Peters... Mr English says his staff and the Treasury have searched again, and they found the document that they denied having. More>>

ALSO:

Midwives On Pay Equity: Historic Bill Of Rights Case For High Court

“We have been left with no choice.” That from Karen Guilliland, the Chief Executive of the New Zealand College of Midwives, as the organisation prepares to file a pay parity discrimination case on the basis of gender under the NZ Bill of Rights Act in the High Court. More>>

ALSO:

Gordon Campbell: On The Children’s Commission Report On CYF

Accusing the overworked and underfunded staff at Child, Youth and Family of a “dump and run culture of neglect” is the kind of luxury that a Children’s Commissioner can afford to indulge in from his own comfy perch in the bureaucracy. More>>

ALSO:

Mt Eden Prison: Serco Inquiry Extended

A two month delay to the Government investigation into prison fight clubs shows the extent of problems within the Serco circus, says Labour’s Corrections spokesperson Kelvin Davis. More>>

ALSO:

Get More From Scoop

 

LATEST HEADLINES

 
 
 
 
 
 
 
 
 
Regional
Search Scoop  
 
 
Powered by Vodafone
NZ independent news