Scoop has an Ethical Paywall
Work smarter with a Pro licence Learn More

Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 

'Stacks on the mill’ a winner for The Terrace

Media Release

October 31, 2013

Stacks on the mill’ a winner for The Terrace


Click for big version.

(The Terrace land preparation JPG):  Demolition rubble is trucked on to The Terrace site and stacked up to four metres high.

As foundation work begins on the new entertainment and office complex The Terrace, in Christchurch, simple Kiwi engineering common sense from Aurecon has meant significant savings in time and money, and reassurance for the developer that the complex is going to be safe.

Geotechnical assessments of the site, on the banks of Christchurch’s Avon River, showed that layers of sand and silty sand approximately 20 metres below ground level were potentially liquefiable in a strong earthquake. While close to the surface, a compressible soil layer - which is the remnant of an old stream bed - had potential to allow foundation settlement under the weight of the building. 

How to make the ground stiffer, was the challenge that faced Aurecon. The company’s Technical Director, Stephen Hogg, says it was known from the outset that staying out of the water table was necessary in order to save time and money.

For the owner of the property, Antony Gough, the solution also had to ensure the safety of the building, which he describes as “paramount”.

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

He says prior to Aurecon’s solution, four options had been considered and rejected:
•       Deep piles down 25 metres, which was rejected due to the potential for future earthquake movement to cause soil lurch (or ground displacements) which could effect the structural integrity of the building
•       Digging out the surface soil and replacing with hard fill imported from local quarries. The extent of dig out was not precisely known and would have involved about 900 truck movements on local roads
•       Remaking the ground to a depth of about three metres by adding cement to the site soils. This is a viable option being used elsewhere in the Christchurch CBD but this particular site is three metres above the water table and major dewatering was likely if soil was removed down to the three-metre level. It was rejected because of cost.
•       Rammed gravel columns, which penetrate the surface soils down to the upper gravel layer. This option was rejected because of cost.
“This is where Aurecon stepped in. They came up with an extremely effective solution similar to the old game of ‘stacks on the mill’.”
Aurecon’s Stephen Hogg says the site was overloaded with heaped demolition rubble to apply weight heavier than what the new buildings will be.

The fill was trucked on to the site from a few hundred metres away and stacked four metres high and left for about four weeks. About 5000m3 of fill was moved (800 truck loads) with a total weight of about 9000 tonnes. The total weight of the building will be about 6000 tonnes.

Surveyors, using precise optical equipment, frequently measured the effect of the heaped demolition rubble on the site. These measurements continued until the settlement effect caused by the stockpiles ceased, at which time the rubble was removed from the site.

“The impact on the roading system and traffic flows was lessened and it was cost effective, good for the environment and good for the economy,” Mr Gough says.

Mr Hogg says the preloading treatment has meant that the buildings do not need complex or deep-seated foundations, as would have been the case. Aurecon also designed a reinforced concrete raft foundation that will allow the buildings to float on top of the pre-compacted soil, which will minimise the effects of differential settlement if deep liquefaction occurs in any future earthquake.

“We gained a month because the raft foundations did not have to be fully designed before pre-loading the site. The design was completed while we waited for the ground to settle. “

The concrete raft will mean the building will float on the upper levels of the ground, providing a robust foundation structure that will be strong and tolerant to settlement.

“It will also distribute the effects of potential differential settlement rather than concentrate the damaging effects, as would be the case with a piled solution or pad foundation solution.

“It will also mean we can easily re-level the building in the future should it be necessary.”

Mr Gough says the fact that work is already under way “is testimony to Aurecon’s smart thinking”.

THE TERRACE FACTS
•       Stage 1 will appear as three buildings on Oxford Tce and one on Hereford St. It will be hospitality on the ground and all of the first floor areas in the Oxford Tce buildings. It will include office space on the upper levels in these buildings. 
•       Stage 2 will be the major large office building on the corner of Cashel and Oxford Tce that will contain approximately 6000m2 of office space and retail plus hospitality on the ground floor. It is due for completion in early 2016. 
•       Stage 3 will complete the Cashel St frontages and is likely to contain retail on the ground floor and a 100 bedroom hotel above. 
•       Stage 4 will be the final stage and it is expected to contain a 320 bay car park sleeved with apartments to sell on both its north face facing Hereford St and the west face facing the central piazza and the Avon River. 

ENDS

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.