Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 


‘Galloping’ Alice Halfway to Waterview


‘Galloping’ Alice Halfway to Waterview




Alice has now reached halfway on the first leg of her long journey underground at Auckland’s Waterview Connection project. The giant tunnel boring machine has constructed exactly 1.2km of the first of the 2.4km-long tunnels to connect the city’s Southwestern and Northwestern motorways.

The NZ Transport Agency’s acting Highways Manager, Steve Mutton, says Alice has been almost unstoppable since resuming tunnelling after a planned two week-long maintenance shutdown in May.

“She has reached a snail’s gallop, with 28 metres progress one day last week – her best day yet. That’s not bad when your top speed is only around 80mm per minute.”

Mr Mutton says that since she began her underground travels from Owairaka to Waterview last November, Alice has averaged around 14m per day excavating spoil and installing the tunnel’s concrete lining.

“At those rates, the machine is well on schedule to complete the first tunnel in late September.”

The world’s tenth largest tunnel boring machine is now 32.5m below the surface. On her 1.2km journey so far, Alice has installed 600 tunnel lining rings, each weighing 100 tonnes and comprising 10 pre-cast reinforced concrete segments. She has also removed 197,000 cubic metres of spoil.

“Technologically, burrowing under Auckland is ‘hungry’ work,” Mr Mutton says. “Alice has consumed $90,000 in power charges and $55,000 for water. It’s another example of the complexity and size of this project.”

On her arrival at Waterview in September, Alice will be turned around over the following three months and re-launched on her southbound journey early next year, building the second (northbound) tunnel as she goes.

Construction of the two tunnels will be completed at the end of 2015, when they will be fitted out with the services needed to operate them. These include ventilation fans, communication systems and fire protection. Sixteen cross passages – one every 150m - connecting the twin tunnels will also be built.

The entire project, which includes the motorway connections either end of the tunnels, is due to be opened in early 2017.

The Waterview Connection completes Auckland’s Western Ring Route. The alternative to the SH1 Southern and Northern Motorways will be 47 kilometres long between Albany and Manukau. The Western Ring Route will improve city and regional transport connections, and is identified by the Government as a Road of National Significance because of its importance to New Zealand’s economy.

The Waterview Connection project is being delivered by the Well-Connected Alliance which includes the Transport Agency, Fletcher Construction, McConnell Dowell, Parsons Brinckerhoff, Beca Infrastructure, Tonkin & Taylor and Japanese construction company Obayashi Corporation. Sub-alliance partners are Auckland-based Wilson Tunnelling and Spanish tunnel controls specialists SICE.

ENDS


© Scoop Media

 
 
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 

17 Year Sentences In Baby Moko Case: Attorney General On Plea Bargain

“The Crown’s decisions in this case, including the decision to accept the manslaughter pleas, were motivated by the need to secure convictions for this horrendous killing and to avoid the significant risk that either of the defendants could escape such a conviction because of evidential issues.” More>>

ALSO:

No Rail For New Harbour Crossing: National Giving Up On Rail In Auckland

The National Government’s decision to scrap two planned rail lines in Auckland shows it is giving up on a city-wide rail network in Auckland, and on thousands of commuters who sit in traffic jams every single day, the Green Party said today. More>>

ALSO:

Gordon Campbell: On The Ombudsman’s Verdict On Paula Rebstock And Ian Rennie

Unfortunately, the brave and damning report by Ombudsman Ron Paterson on the “flawed” and “unfair” inquiry conducted by Dame Paula Rebstock into events at MFAT pulls back the veil on a far wider issue. More>>

ALSO:

Charities' Report: Stressed Families - Overstretched Services

“Like so many of the whānau and families they serve social service organisations are under huge financial stress. The support demanded from desperate people in communities is far outreaching the resources available.” More>>

ALSO:

Detention: Wellingtonians Protest Treatment Of Refugees

Peace Action Wellington (PAW) and around 50 Wellingtonians blockaded the Australian High Commission, creating a symbolic detention centre to protest the Australian Government's policy of mandatory offshore detention for refugees and asylum seekers. More>>

ALSO:

Diver's Alarums: Breach Means Training Provider Must Repay $1.47 Million

The New Zealand School of Outdoor Studies is to repay $1.47 million (GST-exclusive) to the Tertiary Education Commission (TEC) following an investigation which showed that some student enrolments between 2009 -2014 could not be validated and that courses were under-delivered against their agreement with the TEC. More>>

ALSO:

Education: Government Plans Suggest Bulk Funding Return

Plans by the Government to return to bulk funding are likely to see increased class sizes and schools most in need missing out on much-needed resources, Labour’s Acting Education spokesperson Grant Robertson says. More>>

ALSO:

Interim Report: Auckland Looks Long Term To Pay-Per-Km Road Pricing

Aucklanders can expect to be paying variable rates per kilometre to travel on the city's most congested roads under an emerging transport strategy being formulated by the government and the Auckland Council. More>>

ALSO:

Despite Promises: Government Extends Iraq Deployment

Cabinet has agreed to extend New Zealand’s contribution to the joint New Zealand-Australia mission to train Iraqi Security Forces until November 2018. More>>

ALSO:

On The 'Terrorism' Card:

Get More From Scoop

 

LATEST HEADLINES

 
 
 
 
 
 
 
 
 
Regional
Search Scoop  
 
 
Powered by Vodafone
NZ independent news