$8.6M Kotuku detention dam project to begin in earnest

Date: 22 August, 2014

$8.6M Kotuku detention dam project to begin in earnest

Construction on a massive stormwater detention dam designed to better protect Whangarei’s central business district from damaging floods will be underway in earnest within weeks.

Northland Regional Council member Craig Brown who chairs the Urban Whangarei Rivers Liaison Committee, says the council had recently purchased the final property it needed and roughly $2.7M of work to build the dam itself is now scheduled to begin in October.

Councillor Brown says of the estimated $8.6M (GST excl) final cost of the Kotuku detention dam project, about $5 million would have been spent securing the 20 properties needed, with another several hundred thousand dollars to relocate power and other utilities in recent months. The remainder would pay for the dam itself and some associated final landscaping.

He says the contract to build the dam itself – to sit at the ends of Raumanga Valley Road in Raumanga and Kotuku Street, Maunu – has gone to MAP Projects Ltd, which aims to have it finished in autumn next year.

Councillor Brown says MAP is an experienced Rotorua-based civil contracting business that has successfully completed a number of challenging civil construction projects in recent years, including several hydro civil works and dam works and the tender had been awarded after a robust and keenly-contested process.

“This is one of the largest engineering projects the regional council has undertaken and when finished, the 18-metre high dam will hold up to 1.27 million cubic metres of floodwater during heavy rain, about two-thirds the capacity of the existing Whau Valley dam.”

However, Cr Brown says unlike the Whau Valley dam, which provides drinking water to much of urban Whangarei, the Kotuku dam is designed to trap vast amounts of water and then slowly release it over several days.

He says much of the damage caused by floods depends not only on how deep they are, but importantly, also how fast they are travelling.

“In layman’s terms, the Kotuku dam will help address both of these, slowing floodwaters and also cutting flood depths in the CBD by up to half a metre.”

Councillor Brown says the dam will be paid for via an existing targeted rate on more than 17,000 properties in the CBD and contributing catchment areas, but given it had the potential to reduce flood-related damage worth millions of dollars from a single flood, it would be money well-spent.

He says the targeted rate was established under the council’s last Long Term Plan (LTP) in 2012 when the dam’s cost was estimated at about $6.9M (excluding GST).

That figure had been firmed up to its current level based on completion of a more detailed dam design and peer review outcomes, resource consent requirements and given the costs of relocating utilities over the past few months and buying the land needed were now known.

Councillor Brown says the council expects to consult the public next year about changing its Whangarei Urban Rivers Management Rate to accommodate the revised cost as part of work on its new Long Term Plan for 2015-2025.

However, in the meantime, council will continue to work with the Urban Whangarei Rivers Liaison Committee, whose members include representatives from the Whangarei District Council, business and ratepayer communities and tangata whenua.

He says a site blessing is to be organised involving iwi, regional and district councillors will be held soon and among the first steps will be the demolition of five of eight houses that will eventually need to make way the dam, as well as the clearance of some bush. (The houses can’t be relocated due to the way they are built so the first five will be demolished and the remaining three used to accommodate workers during the build and be demolished towards the end of it.)

“Demolition of those homes is due to begin at the start of next month, with the general contractor on site about mid-month and construction beginning in October.”

Councillor Brown says information on the project will be posted on the regional council’s website as the project progresses but says existing presentations and reports are already available via: www.nrc.govt.nz/kotukudam


ENDS

© Scoop Media

 
 
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 

17 Year Sentences In Baby Moko Case: Attorney General On Plea Bargain

“The Crown’s decisions in this case, including the decision to accept the manslaughter pleas, were motivated by the need to secure convictions for this horrendous killing and to avoid the significant risk that either of the defendants could escape such a conviction because of evidential issues.” More>>

ALSO:

No Rail For New Harbour Crossing: National Giving Up On Rail In Auckland

The National Government’s decision to scrap two planned rail lines in Auckland shows it is giving up on a city-wide rail network in Auckland, and on thousands of commuters who sit in traffic jams every single day, the Green Party said today. More>>

ALSO:

Gordon Campbell: On The Ombudsman’s Verdict On Paula Rebstock And Ian Rennie

Unfortunately, the brave and damning report by Ombudsman Ron Paterson on the “flawed” and “unfair” inquiry conducted by Dame Paula Rebstock into events at MFAT pulls back the veil on a far wider issue. More>>

ALSO:

Charities' Report: Stressed Families - Overstretched Services

“Like so many of the whānau and families they serve social service organisations are under huge financial stress. The support demanded from desperate people in communities is far outreaching the resources available.” More>>

ALSO:

Detention: Wellingtonians Protest Treatment Of Refugees

Peace Action Wellington (PAW) and around 50 Wellingtonians blockaded the Australian High Commission, creating a symbolic detention centre to protest the Australian Government's policy of mandatory offshore detention for refugees and asylum seekers. More>>

ALSO:

Diver's Alarums: Breach Means Training Provider Must Repay $1.47 Million

The New Zealand School of Outdoor Studies is to repay $1.47 million (GST-exclusive) to the Tertiary Education Commission (TEC) following an investigation which showed that some student enrolments between 2009 -2014 could not be validated and that courses were under-delivered against their agreement with the TEC. More>>

ALSO:

Education: Government Plans Suggest Bulk Funding Return

Plans by the Government to return to bulk funding are likely to see increased class sizes and schools most in need missing out on much-needed resources, Labour’s Acting Education spokesperson Grant Robertson says. More>>

ALSO:

Interim Report: Auckland Looks Long Term To Pay-Per-Km Road Pricing

Aucklanders can expect to be paying variable rates per kilometre to travel on the city's most congested roads under an emerging transport strategy being formulated by the government and the Auckland Council. More>>

ALSO:

Despite Promises: Government Extends Iraq Deployment

Cabinet has agreed to extend New Zealand’s contribution to the joint New Zealand-Australia mission to train Iraqi Security Forces until November 2018. More>>

ALSO:

On The 'Terrorism' Card:

Get More From Scoop

 

LATEST HEADLINES

 
 
 
 
 
 
 
 
 
Regional
Search Scoop  
 
 
Powered by Vodafone
NZ independent news