Waterview Tunnels Constructions Reaches Halfway

Waterview Tunnels Constructions Reaches Halfway

• One tunnel built, one to go

• 12010 concrete tunnel lining segments in place

• 394,000m3 of spoil removed

The first of the twin road tunnels that will connect Auckland’s Southwestern and Northwestern motorways as part of the NZ Transport Agency’s Waterview Connection project has been built.

Alice, the tunnel boring machine, broke into daylight this afternoon, at the end of her 10-month 2.4km underground journey from Owairaka to Waterview.

The tunnel she has built is the tenth largest diameter tunnel in the world and the longest road tunnel in New Zealand. Once opened in early 2017, it will carry three lanes of southbound traffic up to 40 metres below Avondale and Waterview in west Auckland.

The NZ Transport Agency’s Highways Manager for Auckland, Brett Gliddon, says the tunnel’s completion is a significant milestone for the $1.4bn project to build the new 5km, six-lane motorway link from the Great North Road interchange at Waterview to Maioro Street in Mt Roskill and complete the long awaited Western Ring Route.

“This is a fantastic achievement. Our construction partners on the Well-Connected Alliance completed the breakthrough safely and ahead of schedule,” Mr Gliddon says.

“It is a huge engineering feat for New Zealand, one that is attracting worldwide attention. It demonstrates that with local and international experience and expertise, we can deliver infrastructure to equal the best in the world.”

Mr Gliddon says Alice will now be turned around to bore the northbound tunnel.

“While it is not unusual internationally to turn a tunnel boring machine, what is extraordinary about this turn is the sheer size of the machine and the constricted space in which the manoeuvre will take place.”

At 90m long and weighing 3,100 tonnes, Alice is big. The cutting head and its three trailing gantries will be disconnected and each piece taken one at a time from the completed tunnel and turned.

Only when all of Alice’s parts are in place and reconnected – in early 2015 - will tunnelling resume to construct the second tunnel.

The conveyor system that removes excavated material and other services required for the machine’s operation will also be turned and will follow Alice as she journeys south. By the completion of the second tunnel, they will extend the length of both tunnels - nearly 5km.

A fourth gantry, which operates independently of Alice to install a culvert on the floor of the tunnel, will be the last to be turned. This culvert will carry the services needed for operation of the tunnels once they have been completed.

The machine’s drive south from Waterview to Owairaka is expected to be completed in about October next year. Approximately a year of work will then remain to complete the mechanical and electrical fit-out of the tunnels, including completing ventilation buildings at both ends and constructing 16 cross passages to connect the tunnels.

The entire project - which also involves building the surface connections to the existing motorways, 9km of new cycleway, new community amenities such as walkways, playgrounds and skateparks, and planting approximately 150,000 trees and shrubs – is due to be completed in early 2017.

The Waterview Connection is one of five projects to complete the Western Ring Route as an alternative motorway to SH1 through central Auckland and across the Auckland Harbour Bridge. It is prioritised by the Government as one of its Roads of National Significance because of the contribution it will make to New Zealand’s prosperity by underpinning economic growth and sustainable development for Auckland and its regional neighbours.

The project is being delivered by the Well-Connected Alliance which includes the Transport Agency, Fletcher Construction, McConnell Dowell, Parsons Brinckerhoff, Beca Infrastructure, Tonkin & Taylor and Japanese construction company Obayashi Corporation. Sub-alliance partners are Auckland-based Wilson Tunnelling and Spanish tunnel controls specialists SICE.

As well as designing and building the Waterview Connection, the alliance will operate and maintain the 5km motorway for 10 years from its completion.

Further information about the Waterview Connection is available at the following sites:-

http://www.nzta.govt.nz/projects/waterviewconnection/

www.facebook.com/aliceTBM

ENDS

© Scoop Media

 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

Joseph Cederwall: Building a Community Newsroom

The “Scoop 3.0” Transition Plan
There is good reason to believe that a new path and a better future is possible for Scoop in 2019 as a pioneering independent Media company. A combination of new technology, ideas, institutions and business models and a renewed energy and commitment by the Scoop team, means Scoop aims to be at the forefront of the development of this renaissance that we term ‘News 3.0’.

By opening up Scoop’s structure to community ownership and exploring decentralised technology through the blockchain we can ensure the public has a stake in this enterprise and a say in its development. More>>

 

Gordon Campbell: On Jami-Lee Ross (And The New Hobbit Law)

Clearly, Jami-Lee Ross is not waging a normal form of political warfare, with agreed rules of combat and rational cost/benefit calculations.

This is politics-as-terrorism where everything is being sacrificed by the man in the bomb vest in order to remove Simon Bridges as the leader of the National Party. More>>

Text Messages Released: National On $100,000 Donation(s)
The Botany Electorate of the National Party received 8 donations, and Mr Ross declared 8 donations to us. More>>

ALSO:

Film Industry Working Group:

Three Killed: DOC Supporting Family, Colleagues After Helicopter Crash

The Department of Conservation (DOC) is rallying around family and colleagues of the staff who died in a helicopter crash this morning in Wanaka... The helicopter, with two DOC staff on board, was on its way to undertake tahr control in the Haast area when it crashed. More>>

ALSO:

Political Donations: Greens Call For Tighter Anonymity Rules And Public Funding

“It is clear that those vested interests have a tangible influence on the decision making of political parties. This is a threat to democracy and should change.” More>>

ALSO:

Education Amendment Bill Passes: Urgency Sought For Partnership School Treaty Claim

The claim takes issue with the acts and omissions of the Crown in respect of the closure of Partnership Schools | Kura Hourua. More>>

ALSO:

Salvation Army Paper: Call For Public Housing Investment

To meet these future demands the report suggests the government needs to look beyond the private rental market and begin to invest heavily into home-ownership programmes and more public and social housing. More>>

ALSO:

Cull: Himalayan Tahr Control Operation Proceeding

“The target of controlling 10,000 Himalayan tahr over the next eight months remains. The revised plan provides for a staged control operation with increased reporting to the Tahr Liaison Group...” More>>

ALSO:

Health: Petitions To Fund Breast Cancer Drugs

Women marching to Parliament today, to present two petitions calling for Government funding of vital medicines, have 100% support from a coalition representing than 30 breast cancer organisations. More>>

ALSO:

Animal Welfare Advisory Committee: Report On Rodeo Practices Released

The independent committee that advises the Minister responsible for Animal Welfare, has today released a report on animal welfare in rodeos, together with advice to the Minister making recommendations to improve the welfare of the animals in rodeos. More>>

ALSO:

 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels