Auckland Council’s IS transformation project NewCore
remains on course, according to the latest quarterly
report.
The NewCore Project Update to today’s Finance and Performance Committee shows that the project remains within budget and programme, and has completed the agreed key milestones in the quarter to 30 June 2015.
Auckland Council Chief Operating Officer Dean Kimpton says that he remains pleased with the progress and performance of the team.
“NewCore remains within the agreed budget and is tracking to agreed timelines, the roll-out of the programme remains on course,” he says.
“The team is working very hard and I am pleased that a programme with as much complexity as NewCore continues to meet agreed targets.”
The project budget sits at an actual spend of $42.9 million which is within the approved $46.7m budget for the year.