New Wellington reservoir comes on stream

24 May 2016

New Wellington reservoir comes on stream

Mayor Celia Wade-Brown will tomorrow (Wednesday 25 May) open the valve and connect the new $3.5 million Mt Albert Reservoir to Wellington’s main water supply.

The new reservoir, which is on the ridge above the National Hockey Stadium in Berhampore, holds 2.2 million litres of water, two and a half times the volume of its 105-year-old predecessor, and triples the stored water for the Melrose, Southgate and Houghton Bay areas.

Mayor Wade-Brown says the reservoir is good for Wellington’s resilience.

“The new reservoir will be resilient to a severe earthquake and also provide for the area’s projected population growth,” she says.

Much has been done to earthquake-strengthen Wellington City’s water network over the last 20 years.

“Now almost 70 percent of stored water in Wellington City is in seismically strengthened reservoirs.”

More than 80 percent have automatic shut-off valves so the reservoirs don’t empty if the pipe network is damaged.

“We can all be prepared for an earthquake,” says Mayor Wade-Brown. “Damage could occur in many places on the network and it may not be convenient to collect water from the big reservoirs – we encourage households to store enough water for at least 7 days by installing a rainwater tank as well.”

Councillor Iona Pannett, who chairs the Council’s Environment Committee, says new reservoirs, like the one on Mt Albert, are making the region’s water storage and supply network stronger and safer, and are also being built to have less impact on our parks and reserves.

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

“Unlike its predecessor, this one is below ground,” she says. “The area will be planted and landscaped this winter, restoring and providing additional recreational space in a spot that provides some of the most spectacular views of the south coast.”

Funded by Wellington City Council with construction managed by Wellington Water, the reservoir took 16 months to build. Work involved demolishing the old reservoir, excavating approximately 1500m³ of earth, installing underfloor drainage, laying the slab and erecting the walls.


Quick facts about the new Mt Albert Park reservoir:

· Estimated cost: $3.5 million

· 2200m³ reservoir replaces the existing 810m³ reservoir

· Rectangular in shape

· 25m long x 17m wide x 7m deep

· Reinforced concrete floors and walls

· Precast concrete roof structure

· Excavation involved removing 1475m³ of surplus material including demolition of the existing reservoir

· Work was managed by Wellington Water on behalf of Wellington City Council

ends

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.