New Year Start for Lyttelton Submarine Pipeline Work

New Year Start for Lyttelton Submarine Pipeline Work


Construction of two submarine pipelines to carry wastewater from Governors Bay and Diamond Harbour to Lyttelton will begin in February.

McConnell Dowell have been awarded the contract to build the 5km and 1.8km long pipelines, which are stage two of a four stage $53 million scheme that will end the routine discharge of treated wastewater into Lyttelton Harbour by 2021.

Routine treated wastewater discharges into Lyttelton harbour will end by 2021.

Currently, wastewater from Lyttelton, Governors Bay and Diamond Harbour is treated at wastewater treatment plants in each of the townships before being discharged through outfall pipelines into Lyttelton Harbour.

Under the new scheme untreated wastewater from the townships of Governors Bay and Diamond Harbour will be carried through the submarine pipelines to a new pump station on Simeon Quay in Lyttelton.

It will then be piped through the Lyttelton Tunnel to the Ferrymead pump station and onto the Bromley wastewater treatment plant, where it will be treated. From there it will be discharged out to sea through the Christchurch Ocean Outfall.

Christchurch City Council City Service General Manager David Adamson says work on the first of the pipelines will begin in February and both pipelines should be completed by early 2019.

The pipelines will be buried about one metre deep into the seabed, which is sufficiently deep to prevent anchors catching or the pipes being damaged in storms, tsunamis or earthquakes.

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

"Construction of the marine pipelines will involve pre-fabrication of pipe strings onshore before they are joined together and bottom-pulled out to the required location. A backhoe dredger will then be employed to excavate the trench, lower the pipeline and backfill it," Mr Adamson says.

“McConnell Dowell have considerable experience of this type of work. They have built several marine outfall pipes, including the Christchurch Ocean Outfall eight years ago," he says.


ENDS


© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.