Northpower Fibre UFB connections soaring


Northlanders can’t connect quickly enough to Northpower Fibre’s fast expanding ultra-fast broadband network, with up to 400 people lining up to connect every month.

There are now over 14,000 people connected to the Northpower Fibre network – 12,500 of those in Whangarei alone – giving an impressive uptake figure of over 50%. A further 10,000 people are still able to connect in Whangarei.

Northpower Fibre has just completed livening the final build stage of the Ruakaka UFB network, with all of the 1,370 homes and businesses in the town now able to connect to the fastest broadband in Northland.

Northpower Fibre Chief Executive Darren Mason says the company is continuing to accelerate the expansion of the Northpower Fibre network in 12 towns across Kaipara and Whangarei.

“Our crews completed stage one of Ruakaka three months early and the final stage six months ahead of schedule so they are doing a great job,” says Mr Mason.

“We are all working really hard to bring world class fibre broadband to our regional towns much quicker than planned. Our aim is to be able to ensure that our towns can connect in the shortest possible timeframe which will allow residents and business to get online faster.

“One thing I would urge sports fans to consider if they haven’t already, is that they go to northpower.com/fibre and see if they are able to connect. You will want to be connected to fibre for the best (and uninterrupted) streaming experience of the 2019 Rugby World Cup, so I would encourage anyone to quickly contact their preferred retail service provider or register to connect at northpower.com/fibre/register-your-interest.

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

However, Mr Mason points out that with customer demand to join the Northpower Fibre network so high, people may experience some delays if they wait to get their connection requests in.

“As always, we will do our best to connect as quickly as possible but we do ask that people be patient. So get your orders in early.”

Mr Mason says Mangawhai Village and the remaining part of the Dargaville township will be the next two townships connected to the Northpower Fibre network.

When Mangawhai Village is built, a further 556 people will be able to connect to the UFB network. Mangawhai Village will be released in two stages, the first stage will be in mid-April and the second stage a month later.

When the three build stages in Dargaville East are complete on 13 May, 4 June and 8 July, a further 1,090 people will be able to connect to Northpower Fibre.

The Mangawhai Heads area is also getting UFB with the first part being ready by the end of the year, providing fibre connections for another 626 people.

Uptake rates are climbing quickly in all townships where the UFB network has been completed with Ruakaka already at 20%, Hikurangi at 54%, One Tree Point at 43% and Waipu at 61%.


© Scoop Media

 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.