Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 

Robinson Road Boat Ramp Upgrade kicks off this week

Work on the Robinson Road Boat Ramp in Whitianga, in order to improve it and take pressure off the boat ramp by the wharf, has begun.

The contract has been awarded to Schick Construction and the improvements will include reshaping the boat ramp and installing a floating pontoon. The work is expected to take 8-10 weeks but is weather-dependent.

"We expect the disruption to the existing ramp facility to be kept to a minimum; however, the site for the new facility will be fenced off along with an adjacent site area on the reserve land," says Andrew Scobie, our Council's project manager.

"Where possible, the existing ramp and/or adjacent beach will still be able to be used for launching during most of the construction period; however, there will be times of restricted access and parking," says Mr Scobie.

"To allow the construction to commence we have had to relocate some stored dinghies to adjacent parking area. Please see the site staff for key to relocate your dinghy," says Mr Scobie.

The plan looks at ways to help alleviate congestion at the Whitianga Wharf Boat Ramp, which is a busy area with tourists, ferry passengers and children.

"There has been many investigations historically and proposals into possible sites for the development of a single 'destination boat ramp', to help cater to the growing number of recreational and commercial fishers and boaties," says Allan Tiplady, our Council's District Manager - North.

The first task is to set up the site, including barriers, signage and temporary fencing to restrict access to work areas for the safety of pedestrians.




The work will be carried out during low tides. Excavators will be used to build a rock causeway to access the deepest point.

Once our contractors reach the end of the ramp area we will excavate the seabed to form the new boat ramp approach. The GPS excavators will shape and form the new ramp as it works back to a level above the high water mark.

The rock causeway will be progressively removed and used to form the new ramp shape and upper harbour revetment. Silt will be managed with silt fences and a tepidity curtain and monitored throughout the process.

A large crawler-type crane will be put on site to install sheet piling and sand bags to form a coffer dam which will be emptied of water for the ramp construction.

Once dry enough the construction of the ramp can start with concrete footings and precast panels to form the retaining wall between the old and new ramp.Then final shaping and trimming of the ramp will be done before the boxing, reinforcing and concrete is poured for the new ramp surface.

Then final shaping and trimming of the ramp will be done before the boxing, reinforcing and concrete is poured for the new ramp surface.

Once the new ramp has cured, the timber fencing and piles can be driven for the floating pontoon before the sheet piling is removed.

The new floating pontoon will be floated into position. Finally the reshaped road kerb can be poured and the new asphalt vehicle staging area formed and laid.

The site will be decommissioned and equipment demobilised before cleaning up the site.

Whangapoua Boat Ramp upgrade

Design consultation and consenting for work to rebuild the two-lane concrete boat ramp at Whangapoua and install a floating pontoon is happening this financial year.

Stage one re-construction of the concrete boat ramp is planned to start during 2019/2020, while stage two of the boat ramp upgrade installation of the pontoons is scheduled for 2022/2023.

The existing boat ramp is in a deteriorating condition with cracks in the concrete at the end of the ramp and in between the ramps. is cracked and breaking.

The existing boat ramps were poured at two different levels, which has caused some safety concerns for boat ramp users. The proposed concrete boat ramp will eliminate these issues and the addition of a pontoon will make the boat ramp more user-friendly for boaties.


© Scoop Media

 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

SCOOP COVERAGE: CHRISTCHURCH MOSQUES TERROR ATTACK


Gordon Campbell: On Our Wild West Banking Culture

David Hisco’s nine year stint as CEO of the ANZ bank (while his expense claim eccentricities went by unbothered by board oversight) has been a weird echo of the nine years of social neglect by the previous National government.

The same Sir John Key who denied there was a housing crisis in New Zealand – and who sold his own beach house to Hisco – seems to have also been living in denial in his role as ANZ’s chairman of the board. More>>

 

"Population Density": Stats NZ, Phone Companies To Track People's Movements

Stats NZ is partnering with cellphone companies to launch a new way of tracking people's movements every hour. More>>

ALSO:

QS University Rankings: NZ Ranks Well "Despite Resourcing Constraints"

New Zealand universities continue to do well in international rankings, with the release of the 2020 QS world rankings showing that all eight universities remain in the world’s top 500. More>>

ALSO:

Mosque Attacks: 21 Month Prison Sentence For Sharing Live Stream Video

A Christchurch man who admitted redistributing the livestream video of the mosque killings has been sentenced to 21 months in prison. More>>

ALSO:

Operation Burnham Inquiry: Afghan Villagers Pull Out

The Afghan villagers involved with the inquiry into Operation Burnham say they have lost faith in the process and will no longer take part. More>>

ALSO:

Child 'Uplifts': Children’s Commissioner To Conduct Review

“At the time of the attempted uplift from Hawke’s Bay Maternity Hospital at the beginning of May, our Office shared our views on the critical importance of the mother-child relationship, and the fact that this relationship is denied to too many Māori children”, says the Children’s Commissioner, Judge Andrew Becroft. More>>

ALSO:

Fluro Logo, Definitely Not Racism, Activist Judges: Act Has Conference

“Finally, New Zealanders will have the right to challenge bad laws in court. If the courts find that a law hasn’t been made in accordance with the basic principles of good lawmaking, it can be declared invalid." More>>

ALSO:

 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels