Working on the night moves


Thursday 9 May 2019

The dramatic night lift of a barge, excavator and other machinery over Keepa Road Bridge in Whakatāne marked a smooth transition into the final section of the Kopeopeo Canal for the remediation project.

The Bay of Plenty Regional Council, with co-funding from the Ministry for the Environment, is working with the community to clean up dioxin-contaminated sediment in the Kopeopeo Canal. The canal was contaminated between the 1950s and late 1980s as a result of stormwater discharges from a former sawmill, which treated timber using Pentachlorophenol (PCP).

The Kopeopeo Canal Remediation Project is removing sediment from the canal using a barge-mounted cutter-suction dredge. Sediment is transferred along a pipeline to Geotubes® inside containment sites.

As the barge moves along the canal it needs to be lifted over bridges and pipelines enroute. This lift is the sixth and final of the bridge lifts along the project length.

Deputy Project Manager, Ken Tarboton, said that the process went very smoothly and according to plan.

“All of the other lifts have been in daylight hours, but this was at night because the contractor wanted to minimise any potential traffic-related effects.

“There was a lot of planning and preparation to ensure safety of all the workers on site and to make sure that there were contingencies and back-up plans in place. There is a lot of equipment to move in the right order – first removing all the materials from the barge and setting them aside so we can move the barge itself to the other side of the bridge. Then we needed to put it all back together again on the other side. Full credit to the contractor crane crew and site manager, Des McCleary from EnviroWaste Services Limited for such a smooth lift,” Mr Tarboton said.

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

Dredging will continue along the final section of the canal towards the confluence with the Orini Stream. Four kilometres of the total 5.1km has been dredged to date, marking approximately 80% completion.

Dredging is expected to be completed by the middle of the year, but works will continue on the Keepa Road containment site to cover and start bioremediation of the contained material. During that time, access through the site along the stopbank will remain restricted.

Background
• Images below and higher resolution images are on the website (or on request).
Timelapse video of the move.
• Detailed information on the Kopeopeo Canal Remediation Project can be found at www.boprc.govt.nz/kopeopeo
• The Bay of Plenty Regional Council (Rivers and Drainage Group) is working with the community to clean up dioxin-contaminated sediment in the Kopeopeo Canal. The canal was contaminated between the 1950s and late 1980s as a result of stormwater discharges from a former sawmill, which treated timber using Pentachlorophenol (PCP). While unknown at the time, PCP imported into New Zealand for use in the timber processing industry also included a percentage of impurities that contained dioxins.
• The project will take a staged approach to remove, safely store and treat up to 40,000m3 of sediment.
• The Project is jointly funded by the Regional Council and Ministry for the Environment’s Contaminated Sites Remediation Fund

ends

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.