Last two towers installed for Mt Ruapehu’s new gondola

PRESS RELEASE


Last two towers installed for Mt Ruapehu’s new gondola


MT RUAPEHU, 20 MAY 2019: The final two of 14 towers forming the base of the pathway for Mt Ruapehu’s new gondola are now in place.

Both towers 11 and 7 were a challenge to install, located in difficult to access locations with little access to power and machinery. Tower 11 was also a geologically complex site making it extra challenging.

Whakapapa GM Jono Dean says, “Tower 7 is located in a really tricky spot on a ridge near Hut Flat (called AA Ridge). The challenge here was excavating a large enough hole for the concrete footing and was complicated by the fact that we could only use a small excavator.

“On top of this we needed to bag all of the excavated material and lift it out with the material ropeway, and store it safely until the footing was ready to be back filled. It’s essentially been a hand dug excavation.”

Jono adds that installing Tower 11 was just as challenging. “It’s located in a small outcropping on a location we call ‘2nd Waterfall’. The rock is solid lava so there was no possibility of excavating a traditional footing here. In addition to this we have no way to get an excavator to this site so all the drilling had to be done with handheld units.

“Four large anchor bolts were set into the rock, glued into place and then once set, pull tested to ensure they were sufficiently strong for the foundation to be anchored to. The tower itself is the tallest on the whole lift at 22m.”



Next the haul rope for the gondola will be installed. Pilot lines (which are smaller in diameter) are already in place and these will be used to pull the main haul rope up and then back down the other side of the lift ready to be spliced together. The spool containing the haul rope (as shown in one of the attached pictures) weighs approximately 48,000kg.

Jono says that the Leitner Ropeways team has faced a number of challenges along the way with the gondola project but has overcome them all very efficiently and kept construction progressing as quickly as possible.

“Delays are expected working in an everchanging mountain environment and due to this the opening date for the Sky Waka has moved out a little from the beginning of June to the end. This will coincide with expected opening of the upper mountain at the end of June, our normal Whakapapa season opening date. Happy Valley will open on 1 June as scheduled.”

The new high-speed Sky Waka features fifty Sky Waka gondola cabins with floor to ceiling glass for breathtaking views, internal ski racks, audio and lighting and individual leather seats offering business-class luxury to passengers befitting of the UNESCO Dual World Heritage status of Whakapapa Ski Area. Each cabin accommodates 10 passengers and even the tallest skiers will be able to stand upright in the cabin with more than 2m of internal clearance.

The Sky Waka will run from the Top of the Bruce base area directly to the Knoll Ridge Café. It will transport 2,400 people per hour over the 1.8km in approximately 5 minutes.

As a public benefit entity RAL invests its proceeds back into developing the mountain's facilities and the new gondola forms part of the $100m reinvestment strategy announced by the RAL board in 2015.

ends


© Scoop Media

 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

SCOOP COVERAGE: CHRISTCHURCH MOSQUES TERROR ATTACK


Gordon Campbell: On Our Wild West Banking Culture

David Hisco’s nine year stint as CEO of the ANZ bank (while his expense claim eccentricities went by unbothered by board oversight) has been a weird echo of the nine years of social neglect by the previous National government.

The same Sir John Key who denied there was a housing crisis in New Zealand – and who sold his own beach house to Hisco – seems to have also been living in denial in his role as ANZ’s chairman of the board. More>>

 

"Population Density": Stats NZ, Phone Companies To Track People's Movements

Stats NZ is partnering with cellphone companies to launch a new way of tracking people's movements every hour. More>>

ALSO:

QS University Rankings: NZ Ranks Well "Despite Resourcing Constraints"

New Zealand universities continue to do well in international rankings, with the release of the 2020 QS world rankings showing that all eight universities remain in the world’s top 500. More>>

ALSO:

Mosque Attacks: 21 Month Prison Sentence For Sharing Live Stream Video

A Christchurch man who admitted redistributing the livestream video of the mosque killings has been sentenced to 21 months in prison. More>>

ALSO:

Operation Burnham Inquiry: Afghan Villagers Pull Out

The Afghan villagers involved with the inquiry into Operation Burnham say they have lost faith in the process and will no longer take part. More>>

ALSO:

Child 'Uplifts': Children’s Commissioner To Conduct Review

“At the time of the attempted uplift from Hawke’s Bay Maternity Hospital at the beginning of May, our Office shared our views on the critical importance of the mother-child relationship, and the fact that this relationship is denied to too many Māori children”, says the Children’s Commissioner, Judge Andrew Becroft. More>>

ALSO:

Fluro Logo, Definitely Not Racism, Activist Judges: Act Has Conference

“Finally, New Zealanders will have the right to challenge bad laws in court. If the courts find that a law hasn’t been made in accordance with the basic principles of good lawmaking, it can be declared invalid." More>>

ALSO:

 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels