Draft decision on Wellington Electricity earthquake plan

Issued 1 February 2018
Release No. 89

Draft decision on Wellington Electricity’s $31 million earthquake readiness plan


The Commerce Commission has released its draft decision on Wellington Electricity’s proposal to spend $31 million on improving its network’s resilience to a major earthquake.

Wellington Electricity, which distributes electricity to approximately 166,000 homes and businesses in the wider Wellington region, applied to the Commission to recover the cost of additional earthquake-resilience expenditure in December 2017. The lines company intends to use the additional revenue to bring emergency hardware, mobile substations, switchboards, critical spares and enhanced communication systems into the region, along with earthquake strengthening substations.

The application followed a Government Policy Statement, which outlined the Government’s expectation that the Commission consider options to allow Wellington Electricity to recover resilience-related expenditure that was not anticipated when its price limits were set in 2014.

“After analysing the proposal, we are satisfied that the expenditure is needed and has been costed appropriately to ensure Wellington’s network is better prepared to withstand a major earthquake,” Commission Deputy Chair Sue Begg said.

As a result of the draft decision, Wellington Electricity estimates their typical consumer will contribute around $1.90 more to their average monthly bill of $160. However, when taken together with lower transmission charges signalled by Transpower, we expect monthly bills will reduce in the coming year, assuming the cost of energy and other components do not change.

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

“While the application has been fast-tracked, I want to reiterate that this is a one-off in light of the unique set of circumstances and importance of Wellington being able to function to the fullest extent possible during and after a major emergency,” Ms Begg said.

“Our draft decision also requires Wellington Electricity to demonstrate to us it has made the resilience improvements and it will be penalised for any under-delivery.”

Public and stakeholder submissions on the draft decision are due by 22 February 2018 and can be emailed to regulation.branch@comcom.govt.nz with ‘Wellington Electricity CPP proposal’ in the subject line. We expect to release our final decision by 29 March 2018, with the customised price-quality path set to apply from 1 April 2018.

The draft decision can be found here.


ends

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.