The Minzone and How Low Hydro Levels Are Managed

The Minzone and How Low Hydro Storage Levels Are Managed

There has been some discussion recently on the significance of the Electricity Commission’s Minzone calculation and how the Minzone is updated. This briefing note seeks to clarify the situation about the Minzone.

The Minzone is an analytical tool that helps electricity system planners understand the data about hydro storage levels. It is based on the record of 74 years of hydro inflows into the storage lakes and is intended to provide a 1 in 74 security of supply standard (more conservative than the government’s 1 in 60 year target). That is, in only one year out of 74 would there be shortage that would require further action.

Definition of the Minzone

As hydro storage levels drop due to lack of rainfall, the risk of shortage increases. If storage falls to the Minzone line, it means that from that point there is at least one annual inflow sequence out of the 74 on record which, if repeated, could result in empty reservoirs if no action is taken. It is important to remember that when storage is at the Minzone, there are still 73 out of 74 recorded hydro sequences which, if repeated, do not result in empty reservoirs.

Storage levels approaching, or at, the Minzone do not indicate a “crisis” situation but a need for careful management of the generating system.

When storage is at or below the Minzone, all thermal plants need to be running and all hydro generators need to be conserving water to the maximum extent possible. The Crown-owned Whirinaki reserve energy power plant will be turned on at the Minzone and run to its maximum output, if not already running due to high market prices.

Key Inputs and Adjustments to the Minzone

The Minzone is based on a number of data inputs: for example, the amount of water hydro generators can conserve above minimum outflow requirements, information about thermal fuel supplies, expected thermal plant outages, and the expected output of thermal generating plant.

The electricity market has a voluntary process for notifying plant outages.

Expected outages can change as a normal part of operating thermal generating plant. For example, scheduled maintenance may not need to be as extensive as originally expected, or alternatively may need to be more extensive.

The Electricity Commission monitors the hydro storage situation and other data inputs continuously. It conducts the complicated calculations to update the Minzone when new information merits. Levels of plant outages lasting longer than previously notified can alter the Minzone upwards, indicating increased risk of shortage. Improved plant performance, for example a lesser time out of service than expected, or a cancelled outage would alter the Minzone downwards (lower risk of shortage).

In the April 2006 update of the Minzone, the Commission took into account updated information from Genesis about when a unit at the Huntly station would be fully returning to service. The updated outage schedule meant the output from this generator was expected to be significantly less in April and May, and the Minzone line was adjusted upwards.

Emergency Zone

In addition to the Minzone, the Electricity Commission sets an Emergency Zone below the Minzone. The Emergency Zone is calculated as the point at which risk of shortage is 1 in 10, in contrast to 1 in 74 at the Minzone line.

At the Emergency Zone, the Electricity Commission will institute an emergency conservation campaign, with public messages and possible other measures to induce reduction in electricity usage.

Having the Commission’s campaign not start until the Emergency Zone is reached is designed to allocate the principal responsibility for managing the electricity system to the generating and retailing companies. It may be appropriate for the retailing companies to communicate a conservation message to their customers when storage is well above the Emergency Zone, as the risk of shortage increases. Only when there is a very high risk of shortage would Electricity Commission action be necessary and appropriate.

On-going Monitoring

It is important that there is independent objective analysis of the overall electricity supply situation. This enables all interested parties, both buyers and sellers of electricity, to have equal access to information on which to base their decisions. Until the Electricity Commission was established there was no body to provide such analysis. Although the Electricity Commission’s analysis is independent, close liaison is maintained with the electricity industry to ensure appropriate coordination.

The Commission will continue to monitor the data inputs that influence supply and demand and update the analysis as appropriate. This will from time to time result in changes to the Minzone. Each week there is an update that considers only hydro lake storage levels, which is posted on the Commission’s website.

24 April 2006

ENDS

See... http://img.scoop.co.nz/media/pdfs/0604/Mizone.pdf (Includes current version of the Minzone.)

© Scoop Media

 
 
 
 
 
Business Headlines | Sci-Tech Headlines

 

I Sing The Highway Electric: Charge Net NZ To Connect New Zealand

BMW is turning Middle Earth electric after today announcing a substantial contribution to the charging network Charge Net NZ. This landmark partnership will enable Kiwis to drive their electric vehicles (EVs) right across New Zealand through the installation of a fast charging highway stretching from Kaitaia to Invercargill. More>>

ALSO:

Watch This Space: Mahia Rocket Lab Launch Site Officially Opened

Economic Development Minster Steven Joyce today opened New Zealand’s first orbital launch site, Rocket Lab Launch Complex 1, on the Mahia Peninsula on the North Island’s east coast. More>>

Earlier:

Marketing Rocks!
Ig Nobel Award Winners Assess The Personality Of Rocks

A Massey University marketing lecturer has received the 2016 Ig Nobel Prize for economics for a research project that asked university students to describe the “brand personalities” of three rocks. More>>

ALSO:

Nurofen Promotion: Reckitt Benckiser To Plead Guilty To Misleading Ads

Reckitt Benckiser (New Zealand) intends to plead guilty to charges of misleading consumers over the way it promoted a range of Nurofen products, the Commerce Commission says. More>>

ALSO:

Half A Billion Accounts, Including Xtra: Yahoo Confirms Huge Data Breach

The account information may have included names, email addresses, telephone numbers, dates of birth, hashed passwords (the vast majority with bcrypt) and, in some cases, encrypted or unencrypted security questions and answers. More>>

ALSO:

Rural Branches: Westpac To Close 19 Branches, ANZ Looks At 7

Westpac confirms it will close nineteen branches across the country; ANZ closes its Ngaruawahia branch and is consulting on plans to close six more branches; The bank workers union says many of its members are nervous about their futures and asking ... More>>

Interest Rates: RBNZ's Wheeler Keeps OCR At 2%

Reserve Bank governor Graeme Wheeler kept the official cash rate at 2 percent and said more easing will be needed to get inflation back within the target band. More>>

ALSO:

Get More From Scoop

 
 
 
 
 
 
 
 
 
Business
Search Scoop  
 
 
Powered by Vodafone
NZ independent news