Siemens seeks to support Australian supplier for wind towers


Siemens seeks to support Australian supplier for wind towers

Siemens Ltd, the turn-key supplier of TrustPower’s Snowtown II wind project, is working with newly established Australian wind tower supplier E & A Contractors a wholly owned subsidiary of E & A Limited to procure a portion of the 90 wind towers for the newly commenced wind farm development.

During the procurement phase, Siemens set a target of sourcing 50 percent of the wind towers from local Australian supplier RPG. RPG, a well-known Australian wind tower supplier has recently been placed into Voluntary Administration. E & A Contractors has secured the key personnel and assets used by RPG in the manufacture of wind towers and will incorporate both the personnel and assets into its existing fabrication and manufacturing business at Whyalla. During this transitional phase, Siemens and E & A are working collaboratively to meet the high international standards of the project and enable 20 of the towers to be supplied locally within the manufacturing timeframe of mid next year.

E&A Limited, Executive Chairman Stephen Young said:

“We are pleased to be developing an opportunity to secure a local contract for the towers. Our dialogue with Siemens is progressing positively, and we are looking forward to expanding our business in Whyalla with the aim to supplying towers to the Snowtown II wind farm and to retain a strong wind tower business in South Australia”

The initiative has been supported by the Federal Government and both parties acknowledge their assistance in facilitating a working relationship for the re-establishment of the company in Whyalla.

Siemens Ltd Vice President David Pryke says:

“As part of this great project we have actively collaborated with Australian suppliers to supply the
[more]


towers locally. E & A have demonstrated strong business acumen and a commitment to re-establishing the wind tower business for South Australia by acquiring the key assets and people of RPG. Snowtown II is a significant project for South Australia and will supply 180,000 homes with renewable energy – this will be South Australia’s largest wind farm and is an important step in building a sustainable future for Australia.”

Siemens is discussing the supply timeframe with E&A and will endeavour to work closely with the company to provide them an opportunity to establish their business in a mutually agreed timeframe to support the build of the Snowtown II wind farm.


[ends]

© Scoop Media

 
 
 
 
 
Business Headlines | Sci-Tech Headlines

 

Sky City : Auckland Convention Centre Cost Jumps By A Fifth

SkyCity Entertainment Group, the casino and hotel operator, is in talks with the government on how to fund the increased cost of as much as $130 million to build an international convention centre in downtown Auckland, with further gambling concessions ruled out. The Auckland-based company has increased its estimate to build the centre to between $470 million and $530 million as the construction boom across the country drives up building costs and design changes add to the bill.
More>>

ALSO:

RMTU: Mediation Between Lyttelton Port And Union Fails

The Rail and Maritime Union (RMTU) has opted to continue its overtime ban indefinitely after mediation with the Lyttelton Port of Christchurch (LPC) failed to progress collective bargaining. More>>

Earlier:

Science Policy: Callaghan, NSC Funding Knocked In Submissions

Callaghan Innovation, which was last year allocated a budget of $566 million over four years to dish out research and development grants, and the National Science Challenges attracted criticism in submissions on the government’s draft national statement of science investment, with science funding largely seen as too fragmented. More>>

ALSO:

Scoop Business: Spark, Voda And Telstra To Lay New Trans-Tasman Cable

Spark New Zealand and Vodafone, New Zealand’s two dominant telecommunications providers, in partnership with Australian provider Telstra, will spend US$70 million building a trans-Tasman submarine cable to bolster broadband traffic between the neighbouring countries and the rest of the world. More>>

ALSO:

More:

Statistics: Current Account Deficit Widens

New Zealand's annual current account deficit was $6.1 billion (2.6 percent of GDP) for the year ended September 2014. This compares with a deficit of $5.8 billion (2.5 percent of GDP) for the year ended June 2014. More>>

ALSO:

Still In The Red: NZ Govt Shunts Out Surplus To 2016

The New Zealand government has pushed out its targeted return to surplus for a year as falling dairy prices and a low inflation environment has kept a lid on its rising tax take, but is still dangling a possible tax cut in 2017, the next election year and promising to try and achieve the surplus pledge on which it campaigned for election in September. More>>

ALSO:

Job Insecurity: Time For Jobs That Count In The Meat Industry

“Meat Workers face it all”, says Graham Cooke, Meat Workers Union National Secretary. “Seasonal work, dangerous jobs, casual and zero hours contracts, and increasing pressure on workers to join non-union individual agreements. More>>

ALSO:

Get More From Scoop

 
 
Standards New Zealand

Standards New Zealand
 
 
 
 
 
 
 
 
Business
Search Scoop  
 
 
Powered by Vodafone
NZ independent news