From Wing Tip to Cockpit – 800 Workers in 80 Days

From Wing Tip to Cockpit – 800 Workers in 80 Days

A behind the scenes glimpse into the making of Emirates’ 50th A380 aircraft

Wednesday 20 August, 2014 – It takes 800 workers just 65 to 80 days to assemble, install, test, paint, furnish and deliver an Emirates Airbus A380, the iconic double-decker aircraft that has been creating headlines and delighting travellers since it first entered into service in 2008.

Click here to watch a time lapse video on the making of Emirates’ 50th A380 aircraft which was delivered last month.

Emirates operates the world’s largest fleet of A380 aircraft, with 50 of these graceful feats of modern engineering currently serving 29 global destinations. This includes three daily A380 services between Auckland and Dubai via Australia, with direct connections to A380 flights to cities such as London, Manchester, Paris, Rome, Amsterdam, Barcelona, Munich, Zurich and Moscow.

All of Emirates’ A380s have been furnished and delivered via the Airbus facility in Hamburg.

First, the aircraft fuselage is produced in Hamburg and then transported to Toulouse for the first stage of final assembly. The wing sections, produced in the UK, are also shipped from Airbus’s Hamburg facility to Toulouse. Parts like the fuselage and wings are transferred through a transportation network that includes three specially-commissioned ships to carry the sections from production sites throughout Europe. Over 10,000 bolts are used to connect the fuselage and over 4,000 for the wings.

The first part of final assembly, which takes place in Toulouse, yields an aircraft that is ready for its first ferry flight, sans its interior and paint.

After assembly, each of the five sections of the fuselage are tested by engineers, and then the aircraft is off to Hamburg for painting and cabin furnishing. It takes 30 people approximately 10 days to paint the A380, which has a surface area of 3,150 square meters - approximately the size of seven professional basketball courts. Over 500 kilogrammes of paint is needed just to give the aircraft its white colour.

Cabin furnishing, to install Emirates’ distinctive on-board facilities come in the final stages of the assembly process. It takes about 33 working days to furnish the 550 square metre cabin area on-board the Emirates A380. This includes all seats, galleys, crew rest areas, the unique shower-spa and private suites in First Class, the on-board lounge located at the back of the Business Class cabin, and the award-winning ice inflight entertainment system in all cabins.

Emirates received 13 of the giant double decker aircraft in the last year. Over 28 million passengers have travelled on the Emirates A380 over the last six years of operations, and more travellers can look forward to the experience as Emirates adds more A380 destinations to its route network. New A380 destinations planned for this year include: Frankfurt on 1st September, Dallas on 1st October, San Francisco on 1st December and Houston on 3rd December.

ends

© Scoop Media

 
 
 
 
 
Business Headlines | Sci-Tech Headlines

 

Crown Accounts: Government Ekes Out Six-Month Surplus Of $9M

The New Zealand government eked out a tiny surplus in the first six months of the fiscal year as growth in domestic consumption lifted the goods and services tax take, while uncertainties over the Kaikoura earthquake costs meant expenses were less than expected. More>>

ALSO:

Almost 400 Jobs: Shock At Cadbury's Dunedin Factory Closure

Workers at Cadbury in Dunedin are reeling after learning this morning that the iconic Cadbury factory is to close, with the loss of almost 400 jobs... “The company had reported it was doing well and this has come out of the blue,” says Chas. More>>

ALSO:

Transport: Boards Of Inquiry For Auckland Roading Projects

Boards of Inquiry have been appointed to decide on two significant Auckland roading projects in a move which will get a decision by the end of the year, Environment Minister Dr Nick Smith and Conservation Minister Maggie Barry announced today. More>>

ALSO:

Three Months On: Quake Reciovery In Kaikōura And Elsewhere

Three months after the magnitude 7.8 earthquake on 14 November, encouraging recovery progress is being made in affected communities. More>>

ALSO:

Jetstar, Qantas For Govt Transport: Government Still In Talks With Air NZ

The government is still negotiating with national carrier Air New Zealand in a cross-agency air travel contract that will add a number of new airlines to the list of approved flyers. More>>

ALSO:

Get More From Scoop

 
 
 
 
 
 
 
 
Business
Search Scoop  
 
 
Powered by Vodafone
NZ independent news