Middlemore: Board was pressured to settle for $3m

Phil Pennington, Reporter

Newly released documents show the Counties Manukau District Health Board reluctantly settled for $3 million compensation for one of it worst leaky buildings.

Photo: RNZ / Claire Eastham-Farrelly

Board members said they were being 'time-crunched' and the deal was unfair, but were told the builder Hawkins would not budge even though the cost of fixing its poor workmanship was going up and up.

The minutes of five board meetings addressing the leaky buildings have been released to RNZ under the Official Information Act, after the intervention of the Ombudsman when the DHB initially refused to release them back in March.

The board is told in November 2016 that a report from an independent mediator "showed that Hawkins Construction failed in their work".

Most of the minutes do not give the name of who is speaking.

Read the full minutes here

Timeline shows costs escalating

November 2016 meeting: Hospital management tell the board: "There is $6M of work to be done to remedy the situation, split 50/50" between Hawkins and the DHB.

December 2017 meeting: Under a looming deadline the board debates whether to agree to a contract with Hawkins for $18.8 million. Its own cost consultants advise them it not to accept this contract and to look for another builder.

April 2018: The board signs the contract with Hawkins. Contingencies push the estimated cost to $27.5 million. This amount does not cover the "unquantifiable risks" of sewage repairs, for which $2.5 million extra is being allowed, the minutes show.

Pressure intensifies on the board to agree to settlement and repair contract

The board minutes show Hawkins never budged on the $3 million figure from 2012 - when they confirmed four buildings were leaking badly - and 2017, when they settled out of court with Hawkins.

The settlement covered just one building, the Scott, as the other three had fallen outside a 10-year limit on suing a builder.

The minutes show in March 2017 a board member saying the $3 million offer was "completely unacceptable".

The management team tells the board they've "been trying hard to get Hawkins up to $4M, but they have refused".

Within weeks of the March 2017 board meeting they have accepted the $3 million.

At this same March 2017 meeting, some board members say they do not want to use Hawkins at all for the repair job, saying they have no confidence in it.

However, management told them Hawkins "have a good name", had experience in hospital jobs, and that there would be extra monitoring.

The managers added they had a "high level of confidence" in the repair method Hawkins would use on the Scott building.

Yet just a year later, in a confidential briefing RNZ obtained, the DHB called the method of recladding while patients were still inside, "risky" and virtually "untested" worldwide on such a scale.

In mid-2017 Hawkins was bought by the Australian group Downer.

The board did veer closer to ditching Hawkins. On 6 December it met. Two days later was a deadline in the settlement, after which, Hawkins was no longer obliged to negotiate in good faith on the repair work.

Members debated the advice from their own cost consultants to drop Hawkins and find another builder.

"It feels like we are being time-crunched. We are getting a price that is 45 percent up on this time last year, we are being advised by our cost consultants not to take it, Hawkins are being inflexible and have an unfair margin."

"The $18.8 million [contract] is not the problem, the problem will be when the building is opened up and what might be found."

"What about the contingency on this building, likely to be 50 percent on top."

They raise the prospect of the bill topping $32m and triggering a review by the Office of the Auditor-General.

"What would they say about the decision we are going to make now - the margin was unreasonable; you had advice from external experts; and, it was a sole source arrangement."

The board opted to try to push Hawkins down to $16 million to reclad the Scott.

It didn't work.

The cost of recladding all four buildings - Scott, McIndoe, KidzFirst and Manukau Superclinic - is now being estimated by the DHB at about $70 million.

Another 11 buildings also have multiple problems with leaks, asbestos or seismic issues.

RNZ is seeking comment from Downer about Hawkins.

In March, Downer told us that "Hawkins 2017 Limited has been negotiating with CMDHB in good faith to finalise the construction contract for the Scott Building. This process is confidential".

It would not comment on the quality of the original building work.


© Scoop Media

 
 
 
Top Scoops Headlines

 

Gordon Campbell: On Why We Should Be Anxious About Artificial Intelligence

Frankly, the prospect of possibly losing half the existing forms of paid employment to AI does make me feel extremely anxious, given the indifference shown by central government to the downstream social damage caused by the reform process last time around... More>>

ALSO:


Binoy Kampmark: Tom Wolfe The Parajournalist

As New Journalism’s primary advocate, Tom Wolfe headed the field with such experimental forces as Norman Mailer, Truman Capote and Hunter S. Thompson, all dedicated to enriching supposedly factual accounts with excessive flourishes that hurried out the beige in favour of the kaleidoscopic. More>>

Gordon Campbell: On Racism And The Windsors

For all the talk about the modernizing effect that Meghan Markle could have on the Royal Family, the suspicion all along has been that the House of Windsor is resistant to change at any level beyond the purely decorative. More>>

Gordon Campbell: On Prospects Of US Talks With North Korea

On June 12, the leaders of North Korea and the United States will meet across a table in Singapore, and Kim Jong Un must already be feeling giddy at the thought that this meeting is already being described with the word “summit” formerly reserved for meetings between superpowers of equal stature... Image: Steve Bolton NZ's contribution to the IAEA’s work on North Korea

  • United Nations - UN chief ‘optimistic’ over peace efforts
  • David Swanson - Enough is Enough. The Time Has Come to BDS the US - Peace Comes to Korea: Let’s Understand Why
  • CTBTO - CTBTO on North Korea
  • NZ Govt - NZ welcomes talks between North and South Korea
  • Massey University - Nukes to cyber war – NZ security in focus
  • Jim Miles - The Doomsday Machine - Confessions of a Nuclear War Planner
  • UNHCHR - North Korea detente: UN expert urges human rights opening
  • Binoy Kampmark - Trump, North Korea and Post-Olympic Angst
  • Gordon Campbell: On National’s Latest Attempts At Relevance

    Having ignored the existence of massive problems in health and education for nine years in government, it is no longer politically viable for National to maintain the pretence that such problems really don’t exist, or are somehow unworthy of serious concern by rational men of commerce.... More>>