Was MPI also gagged over Ruataniwha concerns?

David
CUNLIFFE
Labour Leader

25 September 2013 MEDIA STATEMENT
Was MPI also gagged over Ruataniwha concerns?

The Department of Conservation was not the only agency to have its concerns about the Ruataniwha Dam silenced by the Government – it appears the Ministry for Primary Industries was also gagged, Labour Leader David Cunliffe says.

“Leaked briefing notes (attached) reveal DOC consulted its colleagues at MPI over the construction of the irrigation dam in the Tukituki Catchment.

“MPI advised it had ‘similar concerns’ and intended to lodge a submission. Those concerns included the adequacy of the phosphorous management, lack of definition of industry best practice, the use of a nutrient management system called OVERSEER and concerns about the economics of the dam.

“However, these concerns were considerably watered down in MPI’s final submission and the Ministry did a 180 degree turn on the economic impacts. The draft said the dam would be negative, the final submission said it would be positive. Why the change?

“MPI’s change adds further murk to the DOC interference scandal already engulfing endangered Minister Nick Smith.

“It’s time the Prime Minister stepped in and brought his renegade minister back into line and gave the public some honest answers,” David Cunliffe says.

ENDS

Ruataniwha_Leaked_Briefing_Notes.pdf --

[The following is based on automated text recognition by Scoop of the PDF linked above. It contains errors. Please refer to the original.]

BRIEFING NOTES - PLAN CHANGE 6 TO THE HAWKES BAY REGIONAL RESOURCE MANAGEMENT PLAN (TUKITUKI CATCHMENT) AND RUATANIWHA WATER STORAGE SCHEME (RWSS)

Plan Change 6 - Tukituki Catchment

The Hawkes Bay Regional Council (HBRC) notified Plan Change 6 to the Regional Plan for the Tukituki Catchment, this was subsequently referred to the EPA and has now been called in and will be considered by a Board of Inquiry (BOI). The same BOI will also consider resource consents lodged by the Hawkes Bay Regional Investment Company to construct a 90 million cubic metres storage reservoir to supply a community irrigation_ scheme to irrigate (and intensively manage) approximately 25,000 hectares of land, known as the Ruataniwha Water Storage Scheme (RWSS).

The key current land and water management issues for the Catchment are –

• Excessive periphyton growths affecting recreational, amenity and freshwater values

• Low flow conditions affecting fishery values.

• Increased demand for water for irrigation.

Approach to Water Qualitv management in PC 6

• Controlling periphyton growth as a key indicator of freshwater health. Periphyton growth is influenced by both Nitrogen (N) and Phosphorous (P).

• The Plan change proposes managing only P on the basis that most of the lower catchment in the “main stems” is P limited. The plan change allows significant increases to N levels, following research undertaken by NIWA relating to the toxicity levels of N and fish tolerance.

• N limits proposed are much higher (c.f. 300-500%) than the current ANZECC Guidelines for chronic toxicity.

• Farm management practices are then approached on the basis that existing uses are “grand parented" but any increases in leaching rates (to the newly revised N toxicity levels and maintaining P at 2013 levels) as a result of land use intensification will be subject to the consent process.

• The Plan Change proposes higher minimum flows.

Values of Tukituki Catchment

• The Tukituki Catchment contains 18 native fish species, 8 are considered to be “At Risk” and declining according tothe current national threat classification. The diversity of native fish found in the Tukituki catchment is relatively high and the non-migratory dwarf galaxias is found in only one other catchment on eastern side of the Ruahines.

• Tukituki catchment was one of four catchments that were ranked as being nationally significant in the RiVAS (Rivers Values Assessment System) of native fish values in the Hawkes Bay Region. It scored 2“d equal highest in the assessment and was identified as a stronghold catchment for inanga, lamprey, koaro and dwarf galaxias.

• The Tukituki Estuary also been classified as being of national importance for fisheries. Numerous threatened and at risk species use the estuary e.g. white heron, bittern, spotless crake, it provides habitat for a number of scarce and rare insect species (e.g. gossamer damselfly). Significant plant species are present including glasswort, shore primrose and arrow grass. lt is a Recommended Area for Protection (RAP) under the department’s Protected Natural Areas Program because of its ecological and biodiversity values

DOC position on the Plan change

• DOC supports the increase in minimum flows to be achieved through the plan change.

• DOC does not oppose in principle the approach of managing periphyton growth as an environmental indicator to protect freshwater values;

• DOC does not oppose in principle the management of periphyton biomass by managing one nutrient where this is shown to be the limiting nutrient, provided sufficient management tools are available to monitor and review the success of this reasonably new approach and if adverse effects become evident there is the ability through the regulatory process to respond and if necessary reverse any adverse effects in a timely manner.

However there are a number of risks associated with the approach adopted by Plan Change 6. These risks/concerns are:

• The reliance on Phosphorous being the controlling nutrient in periphyton growth for all waterbodies in the catchment as supporting information with the plan change indicates that some sub-catchments are co-limited or Nitrogen limited. The “blanket approach” of the management of P may therefore not be sufficient to provide for the life supporting capacity of freshwater in tributaries where periphyton growth is N limited or N/P co-limited, the result being that algae blooms could be more evident in the tributaries.

• How the HBRC manages and responds to any changes in periphyton species composition that may result from increases in N concentrations. For example the mechanisms leading to excess growth of toxic periphyton (e.g. Phormidium sp.) are not well understood and there is some evidence that limiting nitrogen is important as this species may be able to utilise Phosphorus from entrained sediment.

• The Nitrate toxicity research is laboratory based, utilising only a small suite of species, there is a risk of uncertain environmental outcomes when this is applied in the real world, particularly when applied to an entire catchment and particularly where other stressors also come into play, for example water temperature, predation risk, foraging, dissolved oxygen levels - all of which are generally at their greatest during low flows/peak irrigation demand.

• N toxicity testing has not have been undertaken on the most vulnerable native species within the catchment and therefore there is some doubt that the revised N limits will be able to safeguard the life supporting capacity of the water bodies in the Tukituki Catchment for key taxa.

• Potential effect of changes to nutrient discharge levels on coastal values, including the Tukituki Estuary, and effects on wetlands and lakes, especially Lake Hatuma. The plan change is silent on these matters.

• The ability to reverse the problem should adverse effects become evident - i.e. how quickly they can achieve a reduction in the output of nutrients from farm practices.

• The ability for the regulatory process to respond to the lag time for nutrients to reach the rivers and the accuracy of nutrient modelling to simulate this lag process.

• The massive (up to c.500%) increase on N from current levels could have unexpected ecological effects if it occurs rapidly.

• While nutrient limits have been set, and these may reflect the success of land use practices on periphyton growth (also a limit), there are no triggers/limits/targets (e.g. MCI, fish populations, etc.) which assess the effectiveness of the limits in improving or maintaining ecosystem health and lead to actions if an issue becomes apparent that was not previously identified or investigated.

• Reliance on “industry best practice" to reduce and manage P and N sources. These practices are not defined and are to be introduced later, Similarly the plan change does not set nutrient loading or leaching rates at this stage -these are to be introduced at various stages between now and 2020, it is thereforenot possible to assess the effectiveness of these methods to achieve the objectives in the plan.

• Provisions for fencing of waterways are complicated, will be difficult to enforce and may not be effective in reducing P contributions to waterbodies.

Ministg of Primary Industries

We have consulted with our colleagues at MPl who have advised that they have similar concerns and intend to lodge a submission, in summary their concerns are:

- the adequacy of P management provisions to ensure periphyton control ~ lack of definition of industry best practice » use of OVERSEER » some concerns regarding the economics of the Dam.

Other Considerations

• MfE are currently finalising a first round of amendments to the NPS Freshwater Management including the setting of a National Objectives Framework (NOF) and national bottom lines. MOC to be briefed shortly.

• Sets a framework for guiding Councils in setting objectives and standards for attributes of waterbodies with four bands for each attribute from as close to natural state being the A Band to lowest condition being the D band.

• It is anticipated that the N toxicity levels in the NOF will adopt the work undertaken by NlWA through this plan change, however a fundamental difference is that N may need to be managed to lower concentrations for other purposes (e.g. to control periphyton) and that there will be more than one value that will be set to achieve each Band which could also influence land management and discharges.

Recommendation

There are potential precedent effects from the approach to water management in PC 6. lt is recommended that the Director General lodge a submission on the plan change seeking that:

• the BOI consider and obtain further advice on the robustness of the approach to water quality management, preferably obtaining independent advice on the effectiveness of approach in the plan as this approach has the potential to be replicated in other catchments nationwide, and

• safeguards are built into the regional plan to ensure that the risks/effects noted above can be effectively managed and addressed.

Risks

The outcome of any changes to the approach to water quality management and nutrient management may impact on the amount of land that can be intensified and therefore the economic viability of the dam.

DOC position on the RWSS Irrigation Dam

The following approvals from the MOC and DG are needed:

• A Concession has been sought forthe inundation of 23 ha DOC land in the Ruahine Forest Park. lnitial assessments suggest that it is unlikely that the concession could be recommended to be approved. At this stage the department’s advice to HBRIC is that a land exchange under s16A Conservation Act would be preferable. HBRC are currently identifying appropriate land. We understand that the council has high value land available approximately twice the size of the 22ha of DOC land needed for inundation, as part of a property it is purchasing forthe dam. The Concession application is currently on hold but HBRC may still pursue the concession.

• As the dam will block fish passage, an application to the Director- General under the Freshwater Fisheries Regulations will be required.

DOC Position on the RWSS –

• The effects arising from the construction of the dam can be adequately addressed through conditions on the resource consents (but current form of conditions needs work).

• The increased minimum flows and the ability to provide environmental flushing flows associated with the dam are supported.

• If the approach of water quality management in PC 6 is adopted it is recommended that a cautious and adaptive approach to increasing nutrient (N) levels is provided for in the consents until the effects of the significant increase in N concentrations and the success of P reduction in reducing periphyton blooms can be assessed.

• The effects arising from the discharge of contaminants associated with land use intensification hinge on the provisions in the plan change and (depending on the final limits set) may have some bearing on the amount of land that may be intensified.

• ln general less concern regarding the dam construction but the final framework for water management in both the plan change and for the consents will impact on the economic viability of the dam.

• The ‘Biodiversity Offset’ package is not based on an agreed methodology (in fact no methodology at all has been used) and is unlikely to result in a No Net Loss situation; however there has been some verbal acceptance of the package by departmental officials.

Recommendation

• A neutral submission be lodged, seeking that the BOl firstly consider the water management framework in the plan change and the impact on the RWSS consents before considering the consents (King Salmon High Court appeals also raised the matter of dealing with plan changes concurrently with consents).

• Seek amendments to conditions to ensure sound management of effects.

© Scoop Media

 
 
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

Parliament Today: State Opening Of Parliament

The House sits at 10.30am today before MPs are summoned to hear the Speech from the Throne in the Legislative Council Chamber.

The speech delivered by the Governor-General on the Government’s behalf outlines its priorities for this Parliament.

After this MPs will return to the House for the presentation of petitions and papers and the introduction of any bills.

The Government has five notices of motion on the Order Paper which can be debated. These relate to relating to the appointment of the Deputy Speaker, Assistant Speakers, the reinstatement of business in a carryover motion and one on “Entities to be deemed public organisations”. More>>

 

Tertiary Education: Students Doing It Tough As Fees Rise Again

The Government is making it increasingly difficult for Kiwis to gain tertiary education as fees continue to rise and access to student support becomes even more restricted, Labour’s Tertiary Education spokesperson Chris Hipkins says. More>>

ALSO:

Housing, Iraq: PM Press Conference – 20 October 2014

Prime Minister John Key met with press today to discuss:
• Housing prices and redevelopment in Auckland
• Discussions with Tony Abbott on the governmental response to ISIS, and New Zealand’s election to the UN Security Council More>>

ALSO:

Labour: Review Team Named, Leadership Campaign Starts

Labour’s New Zealand Council has appointed Bryan Gould as Convenor of its post-General Election Review. He will be joined on the Review Team by Hon Margaret Wilson, Stacey Morrison and Brian Corban.

ALSO:


Roy Morgan Poll: National Slips, Labour Hits Lows

The first New Zealand Roy Morgan Poll since the NZ Election shows National 43.5% (down 3.54% since the September 20 Election). This isn’t unusual, National support has dropped after each of John Key’s Election victories... However, support for the main opposition Labour Party has crashed to 22.5% (down 2.63% and the lowest support for Labour since the 1914 NZ Election as United Labour). More>>

ALSO:

In On First Round: New Zealand Wins Security Council Seat

Prime Minister John Key has welcomed New Zealand securing a place on the United Nations Security Council for the 2015-16 term. More>>

ALSO:

TPP Leak: Intellectual Property Text Confirms Risk - Jane Kelsey

The US is continuing its assault on generic medicines through numerous proposed changes to patent laws. ‘These are bound to impact on Pharmac if they are accepted’, according to Professor Kelsey... Copyright is another area of ongoing sensitivity... More>>

ALSO:

RMA: Smith Plans Reform To Ease Urban Development

Newly appointed Environment Minister Nick Smith has announced Resource Management Act reform to foster urban development, where high land prices and expensive resource consents are blocking efforts to provide affordable housing. More>>>

ALSO:

Gordon Campbell: On New Zealand getting involved (again) in other people's wars

Apparently, the Key government is still pondering how New Zealand will contribute to the fight against Islamic State. Long may it ponder, given the lack of consensus among our allies as to how to fight IS, where to fight it (Syria, Iraq, or both?) and with whose ground troops, pray tell? More>>

ALSO:

Gordon Campbell: On child poverty, and David Shearer’s latest outburst

The politicisation of (a) the public service and (b) the operations of the Official Information Act have been highlighted by the policy advice package on child poverty that RNZ’s resolute political editor Brent Edwards has finally prised out of the Ministry of Social Development. More>>

ALSO:

Gordon Campbell: On the government’s review of security laws

So the Key government is about to launch a four week review of the ability of our existing legislation to deal with “suspected and returning foreign terrorist fighters, and other violent extremists.”

According to its terms of reference, the review will consider whether the SIS, GCSB and Police are sufficiently able right now to (a) investigate and monitor suspected and returning foreign terrorist fighters… More>>