Meridian announces stop to Project Aqua

Media Release

29 March 2004

Meridian announces stop to Project Aqua

Meridian Energy has today announced it will not continue with Project Aqua, its hydro development project on the Lower Waitaki river.

Meridian chief executive Keith Turner says a combination of circumstances that has emerged means that it is no longer prudent or responsible to continue with the project.

Dr Turner says there are many reasons that have contributed to the decision. No single reason is decisive, but the combination of factors when considered together has led to the decision.

“In essence the decision has been driven by a series of commercial uncertainties which make the risks of continued spending on the project unacceptable.

“Given the huge effort that has gone into pursuing this project by so many people this has been a difficult decision to make. The simple fact is that in the current circumstances, Project Aqua is no longer achievable.”

Dr Turner says among the reasons for making the decision are:

• Decisions made in the High Court last week highlight significant uncertainties around the nature of “water rights”. These are matters of national significance. They will take years to resolve and could materially affect the availability of water in the Upper Waitaki as well as for Aqua.

• It is evident that Aqua cannot now come on stream fast enough to meet electricity demand growth within the next five years. Meridian will now turn its attention to more immediate sources of electricity generation that can become available more quickly.

• Uncertainties concerning the resource consents but in particular: - Whether Meridian would secure a consent - What the conditions of any consent might be - When the consent would be available - How much water the consent would provide

• There is a need to be decisive, particularly for the people of the Waitaki Valley. They have had three years of uncertainty and will face many more years of uncertainty unless a decision is made now.

• The levels of expenditure for this project are substantial. Currently Meridian is investing about $4 million a month to complete preliminary design and comply with consent requirements. The extended consenting timeframe has added to the risks related to these outgoings and they are no longer sustainable.

• Meridian has been advised that, given the uncertainties, financial reporting standards will require all costs to be seen as expenses, and will not be able to be capitalised towards the costs of the project.

• The project is experiencing rapidly growing indirect costs, particularly to service community mitigation, environmental mitigation and irrigation.

• Recently completed geotechnical investigations have provided information that requires design changes for the project, with an adverse impact on project economics.

• The Resource Management Act creates a very difficult process for large projects dependent on water.

“In short, the magnitude of the risks has become sufficient to make it irresponsible to carry on with the project.

“We are required by the Companies Act to be commercially prudent. When we began with Project Aqua we judged the risks to be manageable, but on the basis of what we know now it would not be prudent to carry on.”

“We want to concentrate our efforts on projects that can be deployed more quickly, but we are absolutely committed to finding sustainable solutions for New Zealand’s energy needs.

“We also want to make this decision clear to everyone involved in Aqua, particularly those communities in the Waitaki Valley who have shared with Meridian the uncertainty of the last three years,” Dr Turner said.

ENDS

© Scoop Media

 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

Charlotte Graham: Empowering Communities To Act In A Disaster

The year of record-breaking natural disasters means that in the US, as in New Zealand, there’s a conversation happening about how best to run the emergency management sector and what philosophies best engage and protect communities in the event of a crisis.

How much of the responsibility for a community’s safety in a natural disaster is the Government’s, and how much can be left up to the community themselves? And how do we ensure none of our most vulnerable residents are left behind? More>>

 

CPAG Report: The Further Fraying Of The Welfare Safety Net

New Zealand’s welfare system has undergone a major transformation during the past three decades. This process has seriously thwarted the original intent of the system, which was to provide a decent standard of living for all New Zealanders in times of need... More>>

ALSO:

Signage, Rumble Strips, Barriers: Boost For State Highway Road Safety

Boost for road safety this summer Associate Transport Minister Julie Anne Genter today announced a short term boost in road safety funding this summer and signalled a renewed focus from the Government on introducing safer speed limits. More>>

ALSO:

Risks & Adaptation: Cheaper To Cut Emissions Than Deal With Climate Change

The cost of climate change to New Zealand is still unknown, but a group of experts tasked with plugging the country's information gaps says it will likely be significant and it would be cheaper to cut greenhouse emissions than simply adapting to those changes. More>>

ALSO:

BPS HYEFU WYSIWYG: Labour's Budget Plans, Families Package

“Today we are announcing the full details of the Government’s Families Package. This is paid for by rejecting National’s tax cuts and instead targeting spending at those who need it most. It will lift 88,000 children out of poverty by 2021." More>>

ALSO:

 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured InfoPages