Cablegate: Start of Gas Flow Through West African Gas

VZCZCXRO0844
PP RUEHMA RUEHPA
DE RUEHOS #0780 3471213
ZNR UUUUU ZZH
P 131213Z DEC 07
FM AMCONSUL LAGOS
TO RUEHZK/ECOWAS COLLECTIVE PRIORITY
RUEHUJA/AMEMBASSY ABUJA PRIORITY 9395
RUEHAR/AMEMBASSY ACCRA PRIORITY 1337
RUEHCO/AMEMBASSY COTONOU PRIORITY 0652
RUEHPC/AMEMBASSY LOME PRIORITY 0657
RUEHC/SECSTATE WASHDC PRIORITY 9650
INFO RUFOADA/JAC MOLESWORTH AFB UK
RUEKJCS/SECDEF WASHINGTON DC
RUCPDOC/DEPT OF COMMERCE WASHDC
RHMCSUU/DEPT OF ENERGY WASHINGTON DC
RUEATRS/DEPT OF TREASURY WASHDC
RUEAIIA/CIA WASHINGTON DC
RHEFDIA/DIA WASHINGTON DC

UNCLAS LAGOS 000780

SIPDIS

SENSITIVE
SIPDIS

STATE FOR AF/W, EEB/ESC, INR/AA,
TREASURY FOR ASEVERENS, SRENENDER, DFIELDS
COMMERCE FOR KBURRESS
DOE FOR GPERSON, CGAY
STATE PASS USTR FOR ASST USTR FLISER
STATE PASS TRANSPORTATION FOR MARAD
STATE PASS OPIC FOR ZHAN AND MSTUCKART
STATE PASS TDA FOR NCABOT
STATE PASS EXIM FOR JRICHTER
STATE PASS USAID FOR GWEYNAND AND SLAWAETZ

E.O. 12958: N/A
TAGS: EPET ECIN ECON ENRG PGOV NI
SUBJECT: START OF GAS FLOW THROUGH WEST AFRICAN GAS
PIPELINE DELAYED

REF: LAGOS 000645

1. (SBU) A USAID contractor advising the West African Gas
Pipeline Company (WAGPco) reports that the free flow of
natural gas through the West African Gas Pipeline (WAGP) has
been delayed until at least January 2008. WAGPco had
announced December 5th as the date for starting the flow of
gas. However, due to delays in hydro testing of the onshore
portion of the pipeline, the earliest date the pipeline could
be ready is December 23, 2007. Two additional weeks would
then be needed for commissioning procedures before starting
operations.

2. (SBU) Additionally, the Escravos Lagos Pipeline (ELP)
Branch A is still undergoing repair. Two ELP branches supply
gas to the WAGP; Branch A which brings dry natural gas from
Chevron's onshore gas fields and Branch B which flows wet gas
from Shell's fields. While Branch B has sufficient
quantities of natural gas to support free flow through the
WAGP, alone its gas is too wet. Branch B gas must be mixed
with dryer Branch A gas to fall within WAGP tolerances. Gas
that is too wet for the pipeline would be corrosive.
Nigeria's Minister of State for Energy (Gas) Odusina Emmanuel
has said that Branch A repairs will be complete by December
15th, however the USAID contractor believed that date will
slide.

3. (SBU) Comment: Problems with Chevron's portion of the
pipeline feeding WAGP are well documented (Ref). Even if
repairs to ELP are completed by December 15th, the onshore
pipeline (and a reliable supply to WAGPco customers) remains
vulnerable to vandalism. End Comment.

4. (U) This cable coordinated with Embassy Abuja.
BLAIR

© Scoop Media

 
 
 
World Headlines

 

UN Rights Office On Syria: The “Monstrous Annihilation” Of Eastern Ghouta

Since the Syrian Government and their allies escalated their offensive against opposition-held Eastern Ghouta on 4 February, there have been more than 1,200 civilian casualties, including at least 346 killed and 878 injured, mostly in airstrikes hitting residential areas... Ninety-two of these civilian deaths allegedly occurred in just one 13-hour period on Monday. More>>

ALSO:

Cyclone Gita: 70% Of Tonga Population Affected

The full scale of destruction is beginning to emerge from Tonga in the aftermath of the severe tropical cyclone Gita. Around 50,000 people, or almost 70% of the country’s population, have been affected, a third of whom are children. More>>

ALSO:


Gita: Samoas Clean Up After Being Swamped By Cyclone

Apia in the wake of Gita Photo: Rudy Bartley The clean up is continuing in the two Samoas after Tropical Cyclone Gita hit on Saturday morning. More>>

ALSO:

Grand Coalition : Germany's two main political parties set to govern under Angela Merkel.

The liberal-conservative Christian Democratic Union (CDU) and the centre-left Social Democrats (SPD) negotiated through the night in a marathon final push to nail down an agreement. More>>


80 Passengers: Kiribati Ferry Disaster

The United Nations Children’s Fund (UNICEF) and the World Health Organization (WHO) are working with the Government of Kiribati to support children, families and communities affected by the recent Butiraoi ferry disaster. More>>

ALSO:

Campbell On: the US demonising of Iran

Satan may not exist, but the Evil One has always been a handy tool for priests and politicians alike. Currently, Iran is the latest bogey conjured up by Washington to (a) justify its foreign policy interventions and (b) distract attention from its foreign policy failures. More

ALSO: