https://www.scoop.co.nz/stories/AK1705/S00215/ruataniwha-scheme-review.htm
|
| ||
Ruataniwha Scheme Review |
||
Ruataniwha Scheme Review
A councillor-initiated review of the Ruataniwha Water Storage Scheme will be presented at a special meeting of Hawke’s Bay Regional Council tomorrow.
The Council commissioned a review of the legal, financial, economic, engineering and environmental elements of the scheme, including the impacts and consequences of implementing the Tukituki Plan - also known as Plan Change 6 - with and without the Scheme, as well as the implications of withdrawing from the Scheme.
Overall, the review concludes that the risks associated with the scheme have been extensively assessed and that the Council can have confidence in these risks having been identified and, where possible, quantified and mitigated. Despite this, there are significant risks that remain with both the scheme proceeding and not proceeding.
Based
on the review, it is now up to the Council to decide if they
are comfortable with the overall level of risk in either
direction, and make a final decision on whether the Scheme
should proceed, be abandoned or shelved.
Legal
The
review confirms the Council’s right to withdraw from the
Ruataniwha Scheme. This will likely require a formal public
consultation process to occur before reaching a final
decision. Should the council choose to proceed with the
scheme it does not need to consult again with the
community.
Engineering
The review includes
consideration of alternative dam sites and on-farm storage
but finds these to be considerably more expensive on a
case-by-case ‘volumetric’ basis. It finds the Ruataniwha
Scheme to be the most cost-effective and efficient method of
storing water for Central Hawke’s Bay irrigation at scale.
Seismic risk, gravel management and the reliability of river
inflows have been reviewed, and found to be adequately
assessed and appropriately managed.
Economic
The
review states there is a higher level of uncertainty around
the Ruataniwha Scheme economics, mainly due to the fact it
is not possible to predict future land use. However, it is
concluded that Ruataniwha Scheme water is affordable for a
range of land uses. The scheme is forecast to deliver
between $130 million and $380 million in annual regional
Gross Domestic Product and between 1130 and 3850 new jobs,
depending on more positive or more pessimistic
assumptions.
If the scheme does not proceed high
environmental flow requirements in the Tukituki Plan will
reduce pre-tax farm earnings by $900,000 on average and over
$4 million in very dry years.
Financial
The
Review concludes that financial arrangements relating to the
construction and operation of the Scheme have been
thoroughly scrutinised and present a relatively low risk to
the Council, and that the Council can have confidence that
the risk of financial failure of the Scheme is very
low.
The review also finds a high level of uncertainty in
the timing and quantum of financial returns to Council’s
Investment Company HBRIC Ltd, depending on how quickly water
is taken up by farmers. The returns are forecast - even in
more pessimistic scenarios - to be acceptable over the
longer-term for an infrastructure investment. The review
states the Council must decide whether the rates of return
on its capital are acceptable in light of its broader,
strategic economic and environmental objectives.
Environmental
The review finds the greatest risk and
uncertainty for the Council is the environmental management
challenges for water quality, out of land use in the
Tukituki Catchment. It says substantial environmental risks
and uncertainty exist for the Council in the catchment with
or without the Ruataniwha Scheme.
The review highlights
that meeting the Nitrogen (Dissolved Inorganic Nitrogen or
DIN) limits in all Tukituki sub-catchments by 2030 (as
required by the Tukituki Plan) is highly improbable and may
even be physically impossible. The Review has identified
that the current Tukituki plan has a number of serious
deficiencies which mean that the Plan will struggle to
deliver lower nitrogen levels with or without the
scheme.
Land use on the Ruataniwha Plains is already
dominated by intensive livestock production and the review
concludes that the scheme will need to facilitate land use
away from this to lower forms of nitrogen leaching, such as
arable farming, vegetable cropping and horticulture, such as
apple and grape production.
It says the Ruataniwha Scheme
provides a framework with stronger controls on farms, more
flexibility and economic upside, as well as improving river
flows in dry summer conditions; however, it is not possible
to rule out scheme-enabled irrigation making the current
nitrogen management challenge worse if it cannot transition
land use effectively.
The review says the Council needs
to decide which set of risks it prefers, and which set of
levers offer the best prospects of achieving the objectives
of the Tukituki Plan Change.
What next?
The
Council will formally receive the review report tomorrow. It
will then seek further advice on options for responding to
the review at a subsequent Council committee meeting.
A
formal decision on the future of the scheme is expected to
be made at the Council meeting on 31
May.
ends