https://www.scoop.co.nz/stories/BU2002/S00280/auckland-airport-completes-runway-review.htm
|
Auckland Airport Completes Runway Review
Wednesday, 19 February 2020, 4:23 pm
Press Release: Auckland Airport
|
Auckland Airport has completed a review into two recent
runway closures which has confirmed the safety of the runway
and its maintenance programme, highlighted factors
contributing to the outages and identified opportunities to
improve the time taken for maintenance repairs.
“The
review identified ways in which we could have improved our
response times, which we have acted on,” said Adrian
Littlewood, Auckland Airport’s Chief
Executive.
“Like all airports, we do have to
occasionally close the runway outside scheduled maintenance
closures for safety reasons such as drone sightings or
clearing debris, but provided the closures are of short
duration there is usually very little impact on
flights.
“The two recent closures were longer and
management takes full responsibility for the delays and we
apologise to the people who had their travel disrupted by
these events.”
He said the review’s completion had
been brought forward from the original estimate of three
weeks because of its importance.
“The review has
identified areas where we could have accelerated this type
of response maintenance work, and we have already put its
recommended steps into effect.”
Mr Littlewood said
that safety always came first, and the airport remained
confident in the safety and integrity of the runway and
airfield maintenance programme, which continued to be
endorsed by independent experts.
There are
approximately 180,000 flights per year and 500 flights per
day at Auckland Airport. As a single runway operation, the
runway is available more than 99% of the time according to
publicly reported annual reliability data.
Longer
unscheduled maintenance outages are rare events, with four
unplanned closures of longer than 15 minutes since January
2018, including the two most recent outages.
Summary
of review
Operational runway
restrictions
- There were two
temporary outages of the runway on 24 January and 6 February
2020 after faults were identified in the corner of two
pavement sections in different locations within the eastern
touch down zone.
- The runway restrictions largely
impacted arriving flights. Maintenance teams take a
safety-first approach and on both occasions they decided to
carry out works immediately instead of during the normal
twice-weekly scheduled runway closure windows for
maintenance (1.30 - 4.30am on Saturdays and
Mondays).
- Faults can occasionally occur in runway
pavement (450-500mm thick) and can be more common in
extended periods of dry and hot weather due to increased
thermal expansion of the concrete.
- Independent
experts have said the unusually hot and dry weather Auckland
has experienced this summer contributed to the faults
occurring.
Maintenance response
time
- The restricted runway
operations on 24 January and 6 February were 43 and 68
minutes respectively – longer than the 20 minute-period
that should have been required to carry out the maintenance
works. This was because of a combination of factors
including the time to assemble specialist tools, the
location of certain resources and the methods chosen to
remedy the faults.
- On 6 February the team took a
safety-first view and adopted a more comprehensive immediate
repair, which required different tools and took longer.
Auckland Airport has a range of maintenance options
available and the review has found alternative methods could
have been applied which would have shortened the
outages.
- On both occasions the review found certain
tools could have been made available in a more readily
accessible location to assist in shortening the response
time. At the time of the most recent incidents our on-call
maintenance response teams were working well away from the
impacted area (airside area spans 300ha) and it took time
for them to relocate.
- Auckland Airport has a policy
of continuous improvement and standard operating procedures
have now been updated to reflect the findings from these
events, including positioning further maintenance kit
airside for rapid response requirements. Further training
will also be provided to support decision making in risk
assessment and remediation
methods.
Asset
management
- The runway is Auckland
Airport’s key asset and our comprehensive asset-management
plan includes continuous monitoring of the airfield with
inspections undertaken multiple times daily, weekly and
monthly.
- Between 2015 and 2019, $48 million has been
spent on pavement replacement and airfield maintenance.
Auckland Airport is investing heavily in its airfield with
$720 million to be spent over the next four years in
upgrading, maintaining and expanding the
airfield.
- Auckland Airport closely monitors and
reviews all requirements for upgrading and maintaining the
airfield infrastructure. Originally constructed in 1965, the
runway has been developed and renewed over the years through
regular and continuous monitoring, maintenance and pavement
replacement – a structured programme of work that follows
recognised standards and is overseen by independent
engineering experts. The programme includes:
- A
continuous programme of budgeted and planned pavement
replacement.
- A comprehensive programme of planned
maintenance to protect the runway’s operations including
twice-weekly scheduled runway closures for planned and
preventative works as is standard practice for airports
around the world.
- Auckland Airport has now increased
monitoring and resourcing, including doubling the frequency
of daily airfield inspections.
- A number of
issues may cause a runway to temporarily close, such as
aircraft emergencies, weather, drone sightings, wildlife or
other foreign object debris (FOD) on the
runway.
- Unscheduled runway outages for maintenance
are also part of operating runways around the world and can
be expected from time to time at Auckland Airport. Providing
for these is an important part of a proactive safety culture
and our Safety Management System to manage risk.
- A
section of the eastern touch down zone (approximately 4.5%
of the runway pavement) where the two recent faults occurred
had already been planned, budgeted and scheduled for
replacement as part of our upgrade programme. Like the rest
of the runway, the pavement in both touch down areas is
continuously monitored by internal and external experts.
There is another small section of runway (approximately 1%)
that has also been scheduled for replacement within the next
five years at the western end of the
runway.
- Auckland Airport has been consulting with
aviation authorities and independent experts on planned
runway works. Design and procurement are already underway
for long-lead items and new jet blast deflector fences to
protect work sites during runway works.
- The airport
discussed the runway works with airlines last year and
identified timing options for the pavement replacement to
take place, with the airport’s preference being September
2020.
Further background
information:
Runway
maintenance
- Faults can occur to the
surface of runway pavement, including in the touchdown zone
subject to impact loading of aircraft. There are a range of
maintenance options which are global standard practice for
concrete pavement runways. These repairs are effective in
minutes.
- These measures are monitored and replaced
with permanent solutions during normal scheduled runway
maintenance closures (1.30 - 4.30am Saturdays and
Mondays).
- We do everything possible to ensure the
runway is clear of FOD, including rubber from aircraft
tyres, rubbish, wildlife or other foreign
objects.
Infrastructure investment
programme
- Auckland Airport is
investing heavily in its airfield with $720 million to be
spent over the next four years in upgrading, maintaining and
expanding the airfield.
- This is part of a
multi-billion-dollar infrastructure investment programme at
Auckland Airport to accommodate the 40 million-plus
passengers and 260,000 flights that are expected by 2044.
This programme of works is focused around eight key anchor
projects, including a new domestic jet facility, roading
improvements to enable public transport and a second
runway.
Home Page
| Business
| Previous Story
| Next Story
Copyright (c) Scoop Media