CMJ traffic bulletin: to Thursday 26 February
Auckland Regional Office
18 February 2004
CMJ traffic bulletin: Sunday 22 to Thursday 26 February
Stage 1 of Transit New Zealand’s Central Motorway Junction upgrade project continues. There are significant closures affecting motorists over the coming week, these are outlined below:
Northbound Carriageway Closure (SH1 Northbound)
-
All northbound lanes over the Newmarket Viaduct closed for
up to 30 minutes, between 1.00am and 3.00am on Thursday, 26
February and Friday 27 February 2004. Traffic will be held
on the motorway during the closures.
CLOSED - at night from 8pm to 6am:
- Sunday 22 until Thursday 26 February
o Symonds Street On-ramp (SH1 Southbound)
o Khyber
Pass On-ramp (SH1 southbound) and Off-ramp (SH1
northbound)
o Northwestern to Southern Motorway Link
(SH16 to SH1)
- Monday 23 until Thursday 26 February
o
Gillies Ave On-ramp (SH1 northbound)
- Tuesday 24 and
Thursday 26 February
o Port to Northwestern Motorway
Link (SH16 Westbound)
o Wellesley Street On-ramp (SH16
Westbound)
There will also be ongoing north and
southbound lane closures at night on the Southern Motorway
between the Gillies Avenue on and off-ramps and the Symonds
Street over-bridge until 2005.
Please choose alternative on- and off-ramps during these times. Motorists are advised that there could be delays.
The CMJ Project
Stage 1
of Transit’s Central Motorway Junction upgrade project
covers the section of motorway between the Upper Queen
Street over-bridge and Gillies Avenue on- and off-ramps and
is scheduled for completion in 2005.
Project information centre: corner of Stanley Street and Alten Road, Grafton, 8.30am – 5.30pm, weekdays.
Phone 0800 ToFreeflow (0800 863 733) or www.transit.govt.nz