Upgrade works on the Anzac Parade / Kowhai Park stopbanks in Wanganui are set to begin next week.

A contract has been awarded to New Plymouth based Whitaker Civil Engineering Ltd to undertake the larger part of the upgrade works, which will comprise raising earth stopbanks, constructing timber retaining walls and concrete floodwalls and modifying roadways within Kowhai Park.

Horizons councilors agreed to the works approximately 12 months ago after an investigation of the existing stopbanks found significant variation in the standard of protection they provided.

Horizons group manager operations Allan Cook says “the works will result in a consistent standard such that a flood that has a 2% probability of occurring in any year, commonly referred to as the 50-year flood, can be contained, without freeboard”.

The present low standard of protection was demonstrated in October last year when a 23-year return period flood was only just contained with hastily erected sandbag walls. Since then, temporary measures have been in place aiding prevention of a stopbank breach.

The works to start next week will generally raise existing stopbanks but also widen narrow sections, improving their ability to withstand high flood levels.

“For safety reasons it will be necessary to close off public access to sections of the park as works progress. Some disruption for the public is unavoidable however we will do our best to minimise that and wherever possible will provide alternative passageways around the works site,” Mr Cook says.

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

The works are expected to be substantially completed within 12 weeks. The estimated cost of the overall flood protection upgrade project, including works in the Matarawa Stream immediately above Anzac Parade, for which tenders are yet to be called, is $1,020,000.

“Completion of the project works will protect an estimated 57 houses from flooding in the 50-year flood and will result in significant savings in wider community disruption, emergency management and clean up costs presently incurred at progressively increasing levels in anything larger than a 20-year flood.”

The works will be undertaken within three separate zones, with works to be substantially completed in each before the next commences.

The first zone comprises the arboretum extending from Georgetti Road to the Matarawa Stream. Works activity will then shift to the area between Dublin Street and Helmore Street, while the final zone comprises the area adjoining the children’s playground.

ENDS

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.