EQ Repairs and Methodology Don’t Meet Building Code

Media Release

24 August 2016

Documents Reveal EQ Repairs and Methodology Don’t Meet Building Code

With the sixth anniversary of the September earthquake in Canterbury only days away, documents obtained by EQC Fix, under the Official Information Act, show hundreds of repairs referred to the MBIE’s Technical Engineering Panel, did not comply with the Building Code.

Accountant Cam Preston, spokesperson for EQCfix.NZ, says an OIA has revealed from the last 200 homes referred to that Panel, 55% not only did not meet the EQC Act or insurance policy standard of “When or as new”, worse they did not comply with the Building Code.

“The issues appear to be related to foundation and subfloor work and although there are simple remedies to some of them to make them compliant with the Code, the main issue is that the Building Code is not and should not have been used, to justify the repairs undertaken on EQ damaged houses,” says Mr Preston. “Of course the building code is relevant to repairs as they must comply with the Building Act however it is not and should never have been the starting point the standard is “When or As New”.

EQCfix.NZ says tens of thousands of homes have either had assessments undertaken or repairs completed on foundations or in the subfloor, and to see from these documents (which cover the last 200 Technical Panel referrals) that 55% were not compliant with the building code, is raising an enormous red flag.

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

“Putting aside for a moment, the obligation of the Insurance Policy to return the house to “When or as new” condition, these documents suggest to us that with Insurance Companies and EQC winding down, anyone who has had an assessment or work done on foundations, should contact their Insurance Company or EQC as soon as possible, to recheck the work,” says Mr Preston. “We believe after the end of this year as employee numbers reduce, it will be much more difficult to get satisfaction if people wait until next year. Public funding for services to help them is drying up as EQC and Insurers try to “turn off the tap” and leave town.”

EQCfix.NZ has letter templates on their website to assist people to request a review, as well as other resources to assist homeowners.

EQCfix.NZ today reiterated the call for an independent inquiry into the way EQC has operated in Canterbury following the quakes.

“MBIE is continuing to support substandard, unconsented foundation repair methods such as “Jack n Pack” and “Epoxy Resin” which camouflages structural damage to foundations that were fully insured for “When New” or “As New” replacement, particularly on TC3 land,” says Mr Preston.

EQCfix.NZ says a planned repair can and should comply with the Building Code but if the repair doesn’t return the house or element of the home that was damaged, to an “when or” or “as new” condition,, then using the Building Code as a justification for the standard of a repair is wrong, as the EQC joint statement makes clear.

“Our message to homeowners is, protect your asset and make sure you get a review of your subfloor work as soon as possible,” says Cam Preston.

Copies of the MBIE slides referred to above are on the Resources page, under the heading, Important Documents, currently item 5.

Ends

Who are we?

http://www.eqcfix.nz/about

EQCfix.NZ was established in May, 2016, following a Declaratory Settlement between EQC and the EQC Action Group. EQCfix.NZ is an independent public justice project whose overarching goal, in a post disaster environment, is to ensure that EQC meets its obligations under the Earthquake Commission Act 1993.

Our aims are:

• to provide information, and if appropriate education programmes, for property owners that better enables them to navigate, understand, and manage the EQC process(es) from claim to reinstatement,

• to co-ordinate and support groups of homeowners to work collectively to address EQC's failures to meet its statutory obligations,

• when a potential EQC performance issue is identified by interested groups / individuals, to investigate and, if possible, to provide homeowners with access to a group solution which is affordable and realistic

• to advocate for an independent inquiry into EQC’s performance, handling and management of Canterbury earthquake claim and reinstatement processes.

• to review and monitor EQC procedures and processes to better ensure that EQC learns from past experience and changes accordingly.


© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.