Scoop has an Ethical Paywall
Work smarter with a Pro licence Learn More

Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 

Takaka Hill repairs: plenty of progress and more is to come

MEDIA RELEASE

15 May 2019

Takaka Hill repairs: plenty of progress and more is to come

People who travel between Golden Bay and Nelson, over the Takaka Hill, will have noticed several areas of improvements* on the road’s repairs this past summer.

The Transport Agency’s Tasman Journeys team has made good progress repairing ten sites in recent months, says NZ Transport Agency Project Manager Reece Foster.

Sections of State Highway 60, the only road link to Golden Bay, were washed out on Takaka Hill after ex-tropical-cyclone Gita* hit the South Island in February last year. Hill traffic was restricted to organised convoys for several weeks until Stop/Go traffic management went in place then traffic lights enabled the highway to be open 24/7.

“Repairs to ten sites within the single lane areas managed with traffic signals have gone well over the 2018/19 summer peak road repair period,” says Reece Foster. “Retaining wall structures and ground stabilisation will be completed over the next two months.

“Design work for the remaining five more significantly damaged sites is now underway by Beca. This work involves repairing large sections of badly damaged road. Our geotechnical team has been hard at work over the summer drilling boreholes and digging test pits to take rock and soil samples. This will ensure the designs for these major repairs will be robust and based on the local conditions at each site. In turn, this will help increase the resilience of this winding hill road in future heavy rain events.”

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

Mr Foster says that construction is scheduled to begin this coming spring aiming to be completed in the first half of next year (2020). This means that hill drivers have another year of traffic lights and short delays before the two-lane highway is restored.

“We appreciate that local people in particular have to factor in short delays on every journey between Golden Bay and the Riwaka side of the hill. Thanks for your patience and for taking care around our crews, who have been working in tightly constrained spaces on some of the repair sites, right inside tight bends or directly below the highway.

“We encourage everyone to maintain cautious driving over the winter when repair work will be scaled back, but lights will be retained, through to the completion of this work.”

Keep up to date on progress of this work and any impacts upon travel here : nzta.govt.nz/projects/sh60-takaka-hill-repairs
*Photo gallery: https://nzta.govt.nz/projects/sh60-takaka-hill-repairs/gallery


Plan ahead for a safe, enjoyable journey. Keep up to date with:
• Traffic updates: nzta.govt.nz/traffic
• Facebook: facebook.com/NZTAsouthisland
• Twitter Top of the South: twitter.com/NZTATotS
• Journey planner: journeys.nzta.govt.nz
• Phone: 0800 4 HIGHWAYS (0800 44 44 49)


© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.