Unexpected Delays With Resurfacing Project Which Has Closed A Major Roundabout Near Invercargill
There has been a delay with progress completing roadworks at Lorneville roundabout at the intersection of state highways 6, 98 and 99 north of Invercargill, says Waka Kotahi NZ Transport Agency.
There was a major machinery breakdown late last week.
Waka Kotahi Southland Highway Maintenance Contract Manager Justin Reid says this will have a further impact on getting this job done on time. “A mobile asphalt plant critical to this piece of work couldn’t be used and won’t be back in action until Wednesday this week (22 February).
“A smaller asphalt plant will be available, however its lower output than the plant we had been using, means delays to completing the roundabout paving as intended. The completion date is now programmed for early next week, 28 February, subject to the weather staying dry.
“We appreciate that this news will be frustrating,” says Mr Reid. “People using the roundabout will have to use the detour route for a bit longer, affecting businesses and the community. We apologise for this and the contractor will be doing their best to get the work done as quickly as possible.”
Plan ahead for a safe, enjoyable journey. Keep up to date with:
· Traffic updates: journeys.nzta.govt.nz/traffic
- Facebook: facebook.com/NZTASouthIsland
- Twitter Otago/Southland: twitter.com/WakaKotahiOS
- Journey planner: journeys.nzta.govt.nz
- Phone: 0800 4 HIGHWAYS (0800 44 44 49)
We have a vision of zero deaths and serious injuries on New Zealand roads. Learn more about:
· Road to Zero – our plan to achieve this vision
· Our vision – video explaining Road to Zero and what we’re trying to achieve
- What Waka Kotahi is doing to support Road to Zero