Transmission Gully contractor suing NZTA for $352m

Transmission Gully contractor suing NZTA for $352m

Transmission Gully contractor Wellington Gateway Partnership is seeking $352 million from the New Zealand Transport Agency over delays in starting the work.

The claim would increase the $850 million construction cost to almost $1.2 billion, amounting to a 41 percent increase. The government's 2019 accounts noted the size of the claim as a contingent liability, and said it "relates to the delays in the commencement of work."

NZTA's contractual disputes in total are tagged as carrying a potential $385 million bill, the bulk of which relates to the Transmission Gully dispute.

The transport agency and Wellington Gateway have been tight-lipped over the claim, which was lodged in February, although NZTA noted it as a contingent liability in its second-quarter report. Despite the reference as a potential liability, NZTA assumed there was “no liability in relation to this claim.” At the same time, it said the project was on time and on budget.

The construction of the 27-kilometre stretch of highway is getting into the final leg, with the road scheduled to open in April next year. In August, NZTA decided tolling the new road would not be suitable and wouldn't make a meaningful contribution to the cost.

Wellington Gateway won the contract to design and build Transmission Gully and maintain it for 25 years. The venture consists of Cimic Group’s PPP unit Pacific Partnerships, Accident Compensation Corp’s investment arm, and global investment manager InfraRed Capital Partners. ACC valued its 45 percent stake at $107.3 million as at June 30, 2019, up from $97.4 million a year earlier.

The PPP contract, signed in 2014, defines a claim as any claim, action, demand or suit for a payment of money, an extension of time, or relief from obligations.

An 80/20 joint venture between Cimic’s CPB Contractors and HEB Construction was sub-contracted to build the four-lane highway and expects to complete the task next year. The JV sought relief after work was delayed by the 2016 Kaikoura quake and flooding around the same time. It was granted a 20-working day extension last year.

Public private partnerships were pitched as a means of reducing the Crown’s risk on major infrastructure projects, while providing investors certainty of work.

When awarding the contract in 2014, NZTA estimated the $850 million net cost of the construction and design was about $25 million less than what it would have been under a traditional procurement process.

The price tag has shifted over the years, including a $985 million estimate in 2004, $1.025 billion in 2008, and $1.3 billion around 2012. After adjusting for inflation, the current $850 million figure would be $895 million in 2019 dollars, and the earlier estimates $1.33 billion, $1.22 billion, and $1.4 billion respectively.

The government valued the Transmission Gully PPP assets and liabilities at $854 million as at June 30, up from $603 million a year earlier.

© Scoop Media

 
 
 
Business Headlines | Sci-Tech Headlines

 

Stats NZ: Unemployment Declines As Underutilisation Rises

The seasonally adjusted unemployment rate decreased to 4.7 percent in the March 2021 quarter, continuing to fall from its recent peak of 5.2 percent in the September 2020 quarter but remaining high compared with recent years, Stats NZ said today. ... More>>

ALSO:

Digitl: The Story Behind Vodafone’s FibreX Court Ruling

Vodafone’s FibreX service was in the news this week. What is the story behind the Fair Trading Act court case? More>>

Commerce Commission: Vodafone Found Guilty Of Misleading Conduct Over 'FibreX' Service

Vodafone NZ Limited has been found guilty of engaging in conduct that was liable to mislead consumers in relation to its FibreX branded broadband service. In a case brought by the Commerce Commission and heard last year, the Auckland District Court ... More>>


Westpac: Announces Strong Financial Result

Westpac New Zealand (Westpac NZ) [i] says a strong half-year financial result has been driven by better than expected economic conditions. Chief Executive David McLean said while the global COVID-19 pandemic was far from over, the financial effect on ... More>>

MYOB: SME Confidence In Economic Performance Still Cautious

New insights from the annual MYOB Business Monitor have shown the SME sector is still cautious about the potential for further economic recovery, with two-in-five (41%) expecting the New Zealand economy to decline this year. The latest research ... More>>

Tourism Industry Aotearoa: Trans-Tasman Bubble Benefits NZ

More people have entered New Zealand than have left since the opening of the trans-Tasman bubble, says Tourism Industry Aotearoa. Since the first flight from Australia to New Zealand took off from Sydney to Auckland on 19 April, the two-way Tasman travel ... More>>