$22.7m Of West Coast Resilience Projects Underway

Hon Simeon Brown
Minister of Transport

Transport Minister Simeon Brown has welcomed news of progress being made by the NZ Transport Agency (NZTA) on the first of several crucial resilience projects underway on the South Island’s West Coast.

“State highways across the West Coast are critical lifelines for communities throughout the region, including for freight and tourism. The Government is committed to ensuring these lifelines are resilient to ongoing severe weather events and other natural hazards,” Mr Brown says.

“Work to improve vulnerable sections of the state highway network along the West Coast are being delivered through the Crown-funded Transport Resilience Fund, with a $22.7m package for the West Coast region.

“With more than a dozen West Coast projects being funded through the Transport Resilience Fund, this work will help build road resilience with significant upgrades for slip management and flood mitigation.

“The first major construction project to start includes river protection works at the Whataroa River on SH6, which began in May. Phase two work on the eastern bridge abutment planned for late July. Similar protection work at the nearby Wanganui River bridge is currently at the end of the design review phase.

“Once this river protection work is completed, it will ensure both bridges are less vulnerable to the intense weather we sometimes see on the West Coast.

“Project teams are also replacing the Douglas No. 2 culvert south of Bruce Bay, replacing the aging culvert with a new 8.8 metre double box culvert.

“The Coalition Government is committed to making sure our state highways are resilient and maintained to the standard Kiwis expect. It’s great to see progress being made on these crucial projects on the West Coast, and I look forward to them being completed.”

Notes:

Projects included in the Transport Resilience Fund for the West Coast Region:

ProjectHazard Type

Project Status

Pre Implementation

Status of Physical Works
SH6 Gates of Haast River ErosionRiver erosionPre implementation work started: Single Stage Business Case (SSBC)

Start date to be confirmed subject to outcome of SSBC.

Construction planning and timing to be confirmed later this year.

SH6 Wanganui River Bridge Abutment ProtectionRiver erosionDesign complete, consenting underway

Phase 1 started April 2024

Phase 2 subject to consenting.

Construction planning and timing to be confirmed later this year.

SH6 Whataroa River Bridge Abutment ProtectionRiver erosionComplete

Phase 1 completed June 2024

Phase 2 started July 2024

SH73 Rock Shelter DSA and StrengtheningOverslipStartedConstruction planning and timing to be confirmed later this year.
SH73 Otira River Bridge Abutment ProtectionBridge scourProject completed (via a different funding method)Completed
SH6 Douglas Culver No.2 ReplacementFloodingApprovedCommenced June 2024
SH73 Candys Bend ScouringRiver erosionDesign complete, SSBC underwayConstruction to start late 2025
SH6 Meybille Bay SlipOverslipOptions assessment and SSBC underway

Start date subject to outcome of options assessment.

Construction planning and timing to be confirmed later this year.

SH6 Buller Gorge Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
Cascade Corner Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
Cobden Hill West Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
Depot Creek Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
Ormon Falls Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
East of McGraths Corner Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
McGraths Corner Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
Whites Bridge West Approach Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
Rocky Point Rock ScalingRockfallSlope stability assessments complete. Design programmedCurrently in design, to be completed by end of FY24/25
SH6 Epitaph Slip – Remote Monitoring Rock ScalingUnderslipCompleteInstallation completed May 2024. TARP (trigger action response plan) threshold development ongoing
SH73 Kellys Creek Bridge Replacement Business CaseBridge replacementOptions assessment and SSBC underwayN/A – Construction not funded under Transport Resilience Fund