|
| ||
Mill Creek: Council recommends fewer turbines |
||
NEWS RELEASE
30 July 2008
Mill Creek: Council
recommends fewer turbines
Wellington City Council
planners have recommended the proposed Mill Creek wind farm
in the Ohariu Valley be given the go-ahead – but with
fewer wind turbines.
The Council planning
officer’s report to the upcoming hearing on Meridian
Energy’s proposed wind farm recommends approval be given
for 25 turbines rather than the 31 turbines proposed by
Meridian Energy.
Council Local Area Planning
Manager Dougal List says the removal of six turbines at the
southern end of the site would lessen the visual and
ecological impact of the wind farm. The six turbines
recommended for removal would have significant impacts on a
number of nearby homes, or are in locations where it is
considered the necessary earthworks would have negative
impacts on streams and wetlands.
Mr List says the
Mill Creek application attracted almost 700 submissions
“and has involved a very challenging assessment for
Council planning staff. We have had to weigh up significant
local impacts against the benefits of renewable power
generation”.
“We have concluded that the
proposal has significant impacts on the local environment
and natural character of the coastal environment. However
this is balanced by the site’s very high suitability for
power generation. It’s very windy – and it’s close to
both a key part of the National Grid and to urban
Wellington.”
Meridian’s resource-consent
application will be considered by three independent
commissioners at a hearing scheduled to start on 11 August.
The hearing is a joint process involving Wellington and
Porirua City Councils and the Greater Wellington Regional
Council. It is expected to run for up to five
weeks.
Though the proposed wind farm is within the
boundaries of Wellington City, Porirua City is also involved
because the project calls for the construction of a private
road from Spicer Valley – in Porirua City. The road would
be used for the delivery of turbines and other equipment and
by assorted construction traffic.
Porirua City
planners have recommended approval for access to the site
over that part of the private road that is within Porirua
City, while Regional Council planners are expected to submit
their report next week.
Up to 140 submitters have
indicated they wish to speak at the hearing.
The
hearing is to be chaired by Auckland-based resource
management consultant David Hill. The other commissioners
are also resource-management consultants - David McMahon
from Christchurch and former Whangarei Mayor Pamela
Peters.
In its consent application, Meridian notes
the project would involve:
31 wind turbines, up to 111m
in height, each with a capacity of 2.3 MW
More than
800,000 cubic metres of earthworks to create turbine
platforms and access tracks and roads
installation of an
internal transmission network
two 70-metre high wind
monitoring masts
erection of a substation and an
operations and maintenance building
realignment of a
section of the existing national grid power lines crossing
the site
a range of temporary construction activities
including but not limited to on-site concrete batching,
geotechnical investigations, extraction and processing of
basecourse aggregate, site offices and ancillary
activities
stream-bed disturbance, diversion and
placement of structures in streams, together with various
discharges ancillary to the construction of a wind
farm.
ends
Review Lanuched: Electoral Commission Wants To Hear From The Public On MMP
Auckland: Transport Plan Goes On The Road
Werewolf Satire: The Other People In Your Neighbourhood
Wellington.Scoop: After protests, Kapiti Mayor Suggests Different CEO Salary System
Werewolf: Why State Capitalism Is Beating The Free Market
Gordon Campbell: On Bank Profits, And Gerry Brownlee’s Asset Sales Plans For Christchurch
Scoop Audio: Charges Possible Over CTV Collapse
Radio NZ Audio: RadioLive To Be Referred To Police Over John Key Show
