Orion services further impacted by Port Hills fire
15 Feb 2017
Orion services further impacted by Port Hills fire
The Port Hills fire has further impacted power
supply to parts of eastern Christchurch, affecting 89,000
customers.
Smoke or flames from the fires caused the Transpower 220 kV line to trip.
Orion has now restored supply to all affected customers.
Supply remains fragile however, due to the continuing fire threat.
ENDS