Investigation work underway on Puhoi-Wellsford
Investigation work gets underway on Puhoi to Wellsford
Development of the Puhoi-to-Wellsford Road of National Significance has taken an important step forward with the NZ Transport Agency awarding a contract for investigation work to decide what alignment the road will follow.
The investigation will take 15 months, and will be undertaken by Sinclair Knight Mertz (SKM), a specialists in engineering and environmental issues.
The NZTA’s acting Regional Director for Auckland and Northland, Tommy Parker, said the investigation was the first step in a process to obtain and protect land for the planned highway, and to apply for the necessary resource consents to construct it.
“A key part of the investigation work will be looking for opportunities that enable the NZTA to deliver this important piece of infrastructure as quickly as possible,” Mr Parker said. “The new highway is going to be built through some difficult and challenging country, and a lot of information and data is needed before we can decide on the best options for constructing it.”
The investigation work will look at a wide range of aspects to the project. These include:
• location and form of road
• social
impacts such as noise, air quality and the effect on the
local community
• tangata whenua and the cultural
impacts of potential routes
• property
impacts
• geotechnical and topography
considerations
• ecological impacts
• affect on
historic areas
• connections to the local roading
network
• walking and cycling access
• potential
construction staging of the work
• cost of the
route
• constructability of the
road
• opportunities for acceleration of the
project.
“The NZTA is working as quickly as possible
to ensure this road is completed on time and within budget,
and this investigation work is the important first step,”
Mr Parker said. “SKM consultants will help us deliver a
high quality solution that will help reduce congestion,
improve safety and encourage economic growth.”
In addition to the investigation works, the NZTA will begin consulting with communities between Puhoi and communities in mid-2010 for their views about the proposed highway.
“This road is important to people in the community, and their feedback will be important for us as we decide on the final alignment and form of the road we are going to construct,” said Mr Parker.
The planned corridor is approximately 38km long. It will include a bypass of both Warkworth and Wellsford. The Puhoi-to-Wellsford section is expected to be substantially completed within 10 years.
The project is one of seven Roads of National Significance which have been identified by the Government as the most urgent roading projects in or near our largest population centres.
For detailed project information go to: http://www.nzta.govt.nz/network/rons/docs/puhoi-wellsford-project-summary-statement.pdf
ENDS
Gordon Campbell: On How US Courts Are Helping Donald Trump Steal The Mid-Terms
Forest And Bird: Government Biodiversity Credit Scheme Welcomed As Opportunity For Restoration
Office of the Ombudsman: Ombudsman Publishes Findings On Ministry Of Education Sensitive Claims Scheme
Nelson City Council: Mayor Welcomes Auditor-General Decision Not To Prosecute Councillor
Johnnie Freeland: Ko Tātou Tātou - Climate Action In Aotearoa Begins With Relationship
Zero Waste Network Aotearoa: Container Return Scheme Bill Would Double Recycling Rates And Put Money Back In Households
Wellington City Council: Statement From The Wellington Mayoral Forum On Options For Regional Governance Reform