State Highway 2 Waioeka Gorge 22nd Project Update
State Highway 2 Waioeka Gorge 22nd Project Update
Over a week ago geologists were concerned about fractures high up on the slope on the Opotiki side (left side of the slope) and the possibility it could cause a small slip failure.
After inspecting this area, they
were confident that this area was relatively stable, but did
agree that it needed to be removed to stabilise the
slope.
The excavator has all
but completed removing the 30,000 cubic metres from the
whale-back area. The machine has been sitting on a 30m
long and 5-8 metre wide platform area at the top of the
whale-back area, benching in a downwards motion to remove
this large volume of material.
Our consultants
Opus have provided us with a plan which outlines how to get
State Highway 2 reopened through this area of the gorge.
As mentioned previously the short term plan will focus on
stabilising the slip face so the diversion road can operate
safely and securely without traffic controllers. What this
plan tells us in detail is how we can stabilise this
challenging slope quickly and effectively. The geologists
have determined the most effective method of doing this is
by benching the identified fractured areas of the slope.
The method currently being used by the excavator
is to pull away at the base of the slip material above the
excavator which causes a natural release, this has been
effective so far, and the plan is to continue with this, but
at a progressively faster rate by having a bulldozer work
simultaneously with the digger to bench the remainder of the
slip face. Once the excavator has dropped slip material down
the chute (see photo) on to the ramp below, the bulldozer
can push the material down the ramp to the waiting trucks.
The excavator will then bench across towards the
Opotiki side and follow the same process as above to remove
the fractured area on the left side of the slope. This area
contains around 3,000 cubic metres of material, we plan to
progress this stabilisation work over the next couple of
weeks
The short term plan also involves maintaining
security of the highway by constructing a rock fall barrier
at the base of the slope. The design and structure of this
rock fall barrier is still to be confirmed, this barrier
will help to stop slip material ending up on the
highway.
Long term plan is likely to take
approximately 2-3 years, this plan focuses on getting the
existing state highway fully reopened, this time-frame is
required to enable the detailed design work to be
undertaken, resource consents to be obtained, funding to be
approved and for the contract to be successfully tendered.
The existing road is buried approximately 20 metres into the
slope, the new road alignment is likely to start 4-5 metres
from the current slope edge. To provide flooding protection
from the Opato Stream, a retaining wall may be required to
add further protection to the state highway once
opened.
These short and long term plans will also
ensure that the temporary diversion road remains largely
unaffected by any work on the slip
face.
ENDS
Gordon Campbell: On How US Courts Are Helping Donald Trump Steal The Mid-Terms
NZ National Party: Judith Collins’ Valedictory Speech
Forest And Bird: Government Biodiversity Credit Scheme Welcomed As Opportunity For Restoration
Office of the Ombudsman: Ombudsman Publishes Findings On Ministry Of Education Sensitive Claims Scheme
Nelson City Council: Mayor Welcomes Auditor-General Decision Not To Prosecute Councillor
Johnnie Freeland: Ko Tātou Tātou - Climate Action In Aotearoa Begins With Relationship
Zero Waste Network Aotearoa: Container Return Scheme Bill Would Double Recycling Rates And Put Money Back In Households

