Rena update #235 – Progress Despite Swells
Rena update #235 – Progress Despite
Swells
Salvage
(Resolve Salvage & Fire)
• Good
progress was made this week, despite salvage operations
being suspended for two days due to high winds and swells.
The project remains on schedule.
• The total
combined weight of steel removed is now approximately 430
tonnes, which is more than 20 per cent of the total weight
to be removed.
• The RMG 280 crane barge is
expected to arrive in port this evening (Friday, 14
September).
• With the arrival of the barge and
a specialised team of divers from the United States,
underwater salvage operations are expected to commence next
week.
• The crane barge – which will operate
from deeper water at the aft end of the bow section - can
raise significantly larger pieces of steel (up to 40 tonnes)
than the helicopters.
• The above water and
underwater operations will run simultaneously.
Braemar Howells/Unimar Update
•
The Braemar/Unimar teams’ new vessel Tasman
Challenger, bought in to help with the removal of debris
from the surrounding seabed as the Rena’s bow
section is cut away, has this week made a strong
start.
• The 26m vessel has been specially
fitted out for the role. Divers are sent down to hook lines
to larger pieces of scrap which are lifted aboard by crane,
and also fill baskets (which can hold over one tonne), with
smaller items.
• Operations Manager Mike
Richards says that more than 20 tonnes of container scrap,
scrap steel, coils of wire and other material has been
successfully recovered in little more than a day. “The
teams have done an excellent job which is continuing at a
steady pace today, while the weather conditions remain
favourable.
• “The Rena owners and
insurers are pleased to receive these reports,” he says.
• Mike Richards says that it took some time
before the Tasman Challenger teams could begin their
work as a special ‘remote mooring’ had to be put in
place. This mooring system allows the vessel to tie up to
buoys instead of putting an anchor down.
• The
mooring system means the Challenger can be quickly moved as
necessary to accommodate the helicopter operations being
carried out by the salvors, Resolve Salvage and Fire, who
are continuing to cut down the bow section of the
Rena.
• On shore, beach cleanup work resumed on
the Coromandel Peninsula early this week, after it had been
halted by last weekend’s stormy weather.
• Mr
Richards says that surveys of Coromandel beaches have been
completed and the survey team has continued south, down
through the Bay of Plenty towards Gisborne.
•
The total number of containers recovered has risen to
996.
Oil spill
response
• Bay of Plenty Regional
Council continues to oversee the Rena oil spill response.
• People are encouraged to report any
sightings of oil to the Bay of Plenty Regional Council
Pollution Prevention Hotline on 0800 884 883.
•
The Regional Council also continues to work with wreck
removal and debris recovery contractors to ensure the risk
of further oil spills is managed. Resolve Salvage and Fire
has an oil spill contingency plan in place and have response
equipment and trained staff at the wreck site. Braemar
Howells has oil spill response equipment on their vessel
patrolling the 2 mile exclusion zone.