Rena Project Update – Salvage Work Restricted
Rena Project Update – Salvage
Work Restricted
Resolve Salvage &
Fire
• Salvage work was
greatly restricted over the past week, with six consecutive
days spent off the water as a result of rough weather.
• The RMG280 crane barge was also unable to operate
during six of the past seven days.
• However, on 12
October the RMG280 was able to lift its largest single piece
of steel from the Rena - 27 tonnes.
• Total steel
landed and weighed this week was only 36 tonnes.
• In
excess of 700 tonnes of steel has been removed overall.
• With the difficult and often dangerous underwater
salvage phase now underway, future operations have become
even more dependant on weather conditions.
• ‘Weather
days’ are anticipated and accounted for in project
timelines. Resolve remains on schedule to complete the
reduction of the bow to 1 metre below the low tide level by
early 2013.
Braemar Howells/Unimar
• Braemar Howells
teams are continuing with beach inspections – focusing on
an area which runs from Mount Maunganui to the coastal
township of Pukehina.
• Braemar Operations Manager Mike
Richards says this work – to pinpoint any remaining Rena
debris – will start from the base of Mauao, with teams
equipped with quad bikes carrying out “close visual
inspections.”
• He says that so far, the results from
this work are very encouraging. “We are naturally keen to
ensure that popular beaches are in good condition for the
expected influx of holidaymakers this weekend.”
• Mr
Richards says the stormy spring weather which has lasted a
whole week forced a halt to the work of divers at the wreck
site. The diver support and recovery vessel Tasman
Challenger was re-deployed to assist with coastal
inspections.
• At sea, patrols are being stepped up to
ensure the safety of boaties, as more small boat owners take
to the water in coming weeks. The tug Maui is continuing
patrols of the wreck site, but we are also planning how best
to deploy a fast response craft should the need arise, Mr
Richards says.
• Mr Richards says boat owners are
reminded that the exclusion zone around the Rena
wreck exists for the safety of people working there, and
boaties.
• The number of containers recovered still
stands 1007 following the identification of another
container from the debris collected last
week.