Scoop has an Ethical Paywall
Work smarter with a Pro licence Learn More

Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 

SCIRT traffic news week starting 23 March

SCIRT traffic news week starting 23 March: Waltham overbridge lanes out from Monday

http://strongerchristchurch.govt.nz/article/scirt-traffic-news-waltham-railway-overbridge-narrows-from-monday

GOOD NEWS

Park Terrace – one-way northbound uplifted as of 20 March

All the restrictions around the southbound closure of Park Tce have been uplifted today.

All turning restrictions at the Bealey Ave/Carlton Mill/Harper Ave intersection have been removed.

THIS WEEKEND

Phillipstown - Ferry Road detours at Ensors/Aldwins Roads intersection

Sunday night, 22 March – major traffic impacts 4 pm to 7 am Monday, 23 March

This Sunday night, from 4 pm, SCIRT’s Fletcher team will work an additional night,on the storm water pipes in this busy intersection near the Mad Butcher, Couplands and other shops which will be open.

• Ferry Road drivers will be detoured left on either side.

• Drivers on Ensors/ Aldwins will have straight through lanes.

• Lanes will be reduced to just one in each direction.

http://strongerchristchurch.govt.nz/work/activity/6558

Please also be aware of other work happening in this area:

Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

NZTA work on Brougham St, Waltham, until 25 April, evenings/ overnight

If you are using Brougham St in the evenings, please note this NZTA project is affecting access to side streets. http://www.tfc.govt.nz/roadworks-brougham-st-between-colombo-st-and-ensors-rd/

HEB work (non-SCIRT) closes base St Andrews Hill Road, Sunday night, 22 March, 7 pm

St Andrews Hill drivers will need to use Mt Pleasant Road or Cannon Hill Crescent/ Bridle Path Road for two months from 22 March. HEB Construction/ CCC is working on the Bridle Path Rd/ St Andrews Hill Road intersection, building a retaining wall and doing storm water work.

The Christchurch Star City to Surf Sunday, 22 March – Hansen Park, St Martins to Ferrymead Playing Fields.

Participants are encouraged to park their cars at the designated parking area atMcCormacks Bay, and catch the special Red Bus service to Centennial Park, Pioneer Stadium. http://www.mapmyfitness.com/routes/fullscreen/64716902/

Transport for Christchurch central city map: http://www.tfc.govt.nz/wp-content/uploads/2015/03/March-20.pdf

CHANGED traffic management:

Waltham railway overbridge & Beckenham shops

Waltham Road overbridge - 23 March lane closures

SCIRT’s Downer team is repairing the overbridge currently. From 23 March there will be lane closures on both sides of the bridge’s concrete median barrier. Expect some delays in the morning and afternoon as the closures will be in place for up to ten days.

http://strongerchristchurch.govt.nz/work/activity/6375

Colombo St, Beckenham shops at Strickland St and Colombo/Tennyson

The traffic management has changed at the Beckenham shops intersection and at Tennyson St this week. Drivers can now get onto Strickland and Somerfield Streets from Colombo St, however access from Somerfield and Strickland is restricted. The right hand turn lane onto Colombo off Tennyson St is also being removed, although drivers can still turn right around the work site. Four sections of a major city wastewater pipe are being relined along Somerfield St, Colombo St and Tennyson St. Thanks to all drivers for taking care and using different routes where possible.

http://strongerchristchurch.govt.nz/work/activity/6555

NEW WORK

Antigua St, Addington, one way south, Hazeldean Road to Disraeli St

SCIRT’s City Care team repaired the wastewater pipes on Antigua St in 2013. Final quality control checks have found two areas where the pipes have dipped due to ground conditions. These now need to be repaired, requiring a one-way south only system on Antigua St south of the railway line from Hazeldean Road to Disraeli St. The detour for northbound drivers is along Disraeli, up Braddon and along Hazeldean Road back to Antigua St. http://strongerchristchurch.govt.nz/work/activity/6564

Hazeldean Business Park, off Lincoln Road, Addington

Part of an earthquake-damaged wastewater pipe on Hazeldean Road, outside of the Hazeldean Business Park, will be repaired in the week of 23 March. One lane will be closed, with detours in place.

Huntsbury Hill, up Ramahana Road – busy

Two SCIRT teams are working on Huntsbury Hill currently – Fletcher on wastewater and Fulton Hogan on storm water. There may be short term one-way systems on and off the hill so drivers are asked to be alert for warnings.

Centaurus Road, St Martins – 26 March expect delays

SCIRT’s Fletcher team is working along a stretch of Centaurus Road between Austin Kirk Lane and Kowhai Terrace (along the river section east of Bowenvale Ave) on wastewater pipe bursting. This will involve either Stop/ Go signals or traffic lights from Thursday, 26 March for two weeks. This may cause delays along Centaurus Road.


Linwood Ave, Avonside Drive end
SCIRT’s McConnell Dowell team will be installing a new storm water pipe across Linwood Ave near the Avonside Drive end. Two-way traffic will remain around the work site but please slow around SCIRT crews.

Brookhaven - Ti Rakau Drive

There will be no exit onto Dyers Road from Ti Rakau Drive for about three weeks. Charlesworth St will be two-way onto Ferry Road.

Hampshire St, Aranui

Hampshire St is currently one-way, northbound only from Lyndhurst Crescent to Wainoni Road, while the vacuum chambers are being installed near the shopping centre. There will be a temporary closure of the Aranui Community Centre car park while the vacuum chambers are being installed. This work will take about three weeks. http://strongerchristchurch.govt.nz/work/activity/6562

City Care crews busy installing vacuum wastewater chambers in Aranui. With close to 750 of these big collection chambers to be installed, City Care and Fletcher are now over the half way mark.

Kerrs Road, Avonside/ Wainoni – traffic islands

SCIRT’s McConnell Dowell team is installing three pedestrian islands on Kerrs Road. Two-way traffic will remain but please take care around the crews.

ONGOING - suburbs

Update on access for South Brighton’s Bridge St bridge

The bridge traffic lanes are back on the new bridge deck so that provides for a more straightforward trip for drivers. Trucks are still not allowed until lanes are wider in a week’s time.

http://strongerchristchurch.govt.nz/article/bridge-st-bridge-update-for-southshore-and-south-new-brighton-drivers

Banks Peninsula hill route, Governors Bay – sorry for unexpected delays

SCIRT’s Fletcher team is extremely sorry for unexpected delays for drivers over Dyers Pass Road this week while the retaining wall is being rebuilt. A semi-permanent traffic light system will be set up over the next week and a half. These lights will also ease the journey up and down the hill for pedestrians and cyclists.

SCIRT thanks everyone for taking care and building in extra time, watching for cyclists and pedestrians. http://strongerchristchurch.govt.nz/article/big-traffic-change-governors-bay-dyers-pass-road-down-to-one-lane-march-august

Marlow Road, Aranui, update

While work is underway on the vacuum wastewater system, there will be a progressive road closure in place on Marlow Road, starting from Pages Road the week starting 30 March. This work will continue until mid-June progressing up Marlow Road towards Hampshire Street. http://strongerchristchurch.govt.nz/work/activity/6545 .

Hampshire St, Aranui, closure Breezes Road end

SCIRT’s City Care team is closing the Breezes Road end of Hampshire St (from Breezes Road to Aldershot St) to install the wastewater main pipe. NB: The Metro bus detour for Pages Road while it is one-way is currently down Hampshire so that will be changed to Gosport St. http://strongerchristchurch.govt.nz/work/activity/6494

Eureka St, Aranui – northbound between Marlow and Rowan from 23 March

While wastewater vacuum work is underway near the intersection of Eureka St and Rowan Avenue, a one-way northbound only traffic system will be in place on Eureka St from Marlow Road to Rowan Ave. No left hand turn off Rowan Ave onto Eureka St. Two-way traffic should be reinstated by mid April. The change is to ensure the Metro bus route is maintained.

Wainoni Road, Aranui, vacuum wastewater installations continue

SCIRT’s City Care team has completed installing the vacuum wastewater main between Breezes Road and Portsmouth St on Wainoni Road. The next stage is installing the 17 vacuum collection chambers in the road shoulder and the lateral pipes to properties. Two-way traffic will be maintained but access to properties may be temporarily restricted.

Bassett St, Burwood – keep supporting the businesses Parnwell and Bassett

A lift station and a pumping station are being built on Bassett St, with the work site reducing the space on the road. There is a plan to extend the range of the traffic light controlled area. But for the time being, the status quo reigns.

Thanks to everyone who is supporting the businesses on Bassett and Parnwell Streets.


© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

InfoPages News Channels


 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.