Waiuku Wind Farm Declined Fast-track Consent
An independent panel has declined resource consent for a wind farm in Waiuku, Franklin.
LET Capital Number 3 Limited applied for resource consent under the COVID-19 Recovery (Fast-track Consenting) Act 2020.
The project would have involved constructing and operating a wind farm with 13 wind turbine generators to supply electricity to the national grid.
The decision comes 154 working days after the application was lodged with the Environmental Protection Authority.
The Environmental Protection Authority is not involved in the decision-making. We provide procedural advice and administrative support to the panel convenor, Judge Laurie Newhook, and the expert consenting panel he appoints.
Read the Waiuku Wind Farm decision report : https://www.epa.govt.nz/fast-track-consenting/referred-projects/waiuku-wind-farm/the-decision/
More about fast-track consenting : https://www.epa.govt.nz/fast-track-consenting
Gordon Campbell: On Children’s Book Classics - The Moomins
Zero Waste Network Aotearoa: Container Return Scheme Bill Would Double Recycling Rates And Put Money Back In Households
Wellington City Council: Statement From The Wellington Mayoral Forum On Options For Regional Governance Reform
MUNZ: TAIC Report On Kaitaki Incident Gives Shocking Picture Of Decline Of NZ Maritime Infrastructure
Greenpeace: New Climate Report Yet More Reason To Reduce Dairy Herd
Better Public Media: Opposing Plans To Scrap The BSA
Internal Affairs: Citizenship Test For Citizenship By Grant Applicants From Late 2027