Scoop has an Ethical Paywall
Licence needed for work use Start Free Trial

Local Govt | National News Video | Parliament Headlines | Politics Headlines | Search

 

Infrastructure To Improve Estuary Health And Network Resilience In Waiwera And Hatfields Beach

Crews work to install the 4.5km wastewater main that will transfer wastewater from a new pump station in Waiwera to Hatfields Beach pump station. Credit: Watercare. Photo/Supplied.

A major environmental milestone is underway at Waiwera, with a $45 million upgrade set to end all treated wastewater discharges into the Waiwera Estuary - a change expected to significantly improve water quality in one of the region’s most sensitive coastal environments.

The wastewater oxidation ponds at the  Waiwera Wastewater Treatment Plant. Credit: Watercare. Photo/Supplied.

The Waiwera water and wastewater upgrade is part of Watercare’s 10 year, $13.8 billion capital works programme (2025 – 2034) to increase network capacity and boost resilience across Auckland.

Watercare head of wastewater planning Andrew Deutschle says removing discharges is a transformational shift for the estuary.

“This work will eliminate treated wastewater discharges into the Waiwera Estuary entirely - a huge win for water quality and the local environment.

“To deliver this, we’re building a new wastewater pump station beside the existing Waiwera Wastewater Treatment Plant and installing a 4.5kilometre pipeline that will connect the new pump station to the Hatfields Beach Pump Station.

Advertisement - scroll to continue reading

“From there, wastewater will be pumped to the Army Bay Wastewater Treatment Plant for higherlevel treatment before being released through the Army Bay outfall.”

Once the new system is operational, the Waiwera Wastewater Treatment Plant will be decommissioned.

The wider programme also includes installing an 840metre replacement watermain to improve reliability and futureproof the network for an expected 1,600 additional residents by 2068.

Watercare project manager Martin Hughes says construction is already progressing, with crews laying the first sections of the wastewater pipeline along Hibiscus Coast Highway and Weranui Road.

“These initial sections were installed using opencut trenching due to steep, winding terrain.

“Now that those sections are in, we can switch to horizontal directional drilling for most of the remaining pipework. It’s faster, less disruptive and more costefficient than open trenching.

“Permanent lane closures - up to 500 metres in length - are currently in place on the northbound lane of Hibiscus Coast Highway, with twoway traffic signals managing vehicles on the southbound lane.

“A shift into a wider work area from late February is expected to ease some congestion.”

Hughes says the team is also coordinating closely with Auckland Transport on repairs to slips near the work zone but remains confident in the timeline.

“The slips have created some minor disruption, however we will reschedule the construction of the new wastewater pipeline to accommodate the slip repairs.

“We’re still on track to deliver the wastewater and water upgrades by the end of the year.

“We really appreciate the community’s patience as we deliver work that will benefit the Waiwera Estuary and support the area’s future.”

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Parliament Headlines | Politics Headlines | Regional Headlines

 
 
 
 
 
 
 

LATEST HEADLINES

  • PARLIAMENT
  • POLITICS
  • REGIONAL
 
 

Featured News Channels