Exploration Well - Momoho 1
Exploration Well - Momoho 1
(Offshore Taranaki Basin, New
Zealand)
Origin Energy Limited, on behalf of the Kupe Joint Venture, advises that as of 12 pm EST on 18 June, the following operations have been completed on Momoho 1:
•
The ENSCO 107 was positioned over the Momoho location and
the necessary
preparations undertaken to commence
drilling.
• The 36 inch hole section was drilled to
180m MDRT (measured Depth below Rotary
Table) and the 30
inch casing set and cemented.
• The 22 inch hole
section was drilled to a final depth of 561m MDRT.
Over
the coming week, the rig is expected to run 18-5/8 inch
casing and commence
drilling the 17 inch hole
section.
Drilling began on 13 June 2008 and progress to
date is summarised as follows:
36 inch 22 inch 17 inch
12-1/4 inch 8-1/2 inch
Planned 170.5m 550m 1,830m 2,855m
3,142.5m
Actual 180m 561m
*Depths are cumulative and
show total well depth measured below the rotary table
(MDBRT).
The well is expected to take approximately 51 days to drill on a dry-hole basis.
Partners in the Kupe
permit PML 38146 are:
Origin Energy Resources (Kupe)
Limited* (Operator) 50%
Wholly owned subsidiaries of
Genesis Energy 31%
New Zealand Oil & Gas Limited (through
its subsidiaries:
National Petroleum Ltd. 12.75%,
Petroleum Equities Ltd. 1.25%
and Nephrite Enterprises
Ltd. 1.00%) 15%
Mitsui E&P Australia Pty Ltd 4%
*a
wholly owned subsidiary of Origin Energy
Limited
ENDS
Stats NZ: Economic Impacts On New Zealand From Conflict In The Middle East – Report
Advertising Standards Authority: ASA Annual Report 2025 - Platform-Neutral Regulation Keeps Pace With Digital Advertising
Science Media Centre: Lead Pipes Banned For New Plumbing – Expert Reaction
New Zealand Young Physicists Trust: Auckland To Host The ‘World Cup Of Physics’ In 2027; Search Begins For Student-Designed Tournament Logo
Oxfam Aotearoa: Top CEO Pay Increased 20 Times Faster Than Workers’ Pay In 2025
Bill Bennett: TUANZ Report - Networks Built, Value Missing