Scoop has an Ethical Paywall
Work smarter with a Pro licence Learn More

Video | Agriculture | Confidence | Economy | Energy | Employment | Finance | Media | Property | RBNZ | Science | SOEs | Tax | Technology | Telecoms | Tourism | Transport | Search

 

Auckland Pipeline Repair: Status Update

Pipeline repair: status update

We have made good progress on the repair activities overnight, having now isolated (stoppled) the south side of the pipe leak. The team is preparing to isolate the north side of the leak today. These are the necessary steps before we can cut the pipe.

Importantly, the refinery remains on track to meet the Wiri delivery window (midday Sunday the 24th and midday Tuesday the 26th).


The Repair in further detail:

On the south side

o The split tee has been welded in place;

o The hole has been cut in the top of the pipe (for stopple access);

o The stopple has been fitted;

o Water has been flushed from the south site northwards, to ensure that the North stopple; site is air-free for welding.


On the North side

o Scanning has confirmed that the pipe is now fully fluid-filled, in readiness for welding;

o The pipe has been prepared for welding readiness.


Today’s activity are on focused on the North side

o fitting the split tee;

o cutting the hole for stopple access; and

o fitting the stopple.

If we achieve all of this today then we move into the next phase of cutting out the damaged section of the pipe, (for which we are busy finalising the necessary hazard assessment).


ENDS


Advertisement - scroll to continue reading

Are you getting our free newsletter?

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.

© Scoop Media

Advertisement - scroll to continue reading
 
 
 
Business Headlines | Sci-Tech Headlines

 
 
 
 
 
 
 
 
 
 
 
 
 

Join Our Free Newsletter

Subscribe to Scoop’s 'The Catch Up' our free weekly newsletter sent to your inbox every Monday with stories from across our network.