Auckland Metro Network Christmas Shutdown

Infrastructure work across the Auckland metro rail network is set to ramp up over the Christmas period during a network wide shut down.

As Aucklanders head out of the city on holiday, work on several projects is scheduled across the network to take advantage of the quieter period.

KiwiRail Chief Operating Officer Todd Moyle says work will focus on track repairs.

"We'll have more than 100 people working over the Christmas and New Year period across the network. Additionally, preliminary work on Papakura to Pukekohe electrification, the Westfield and Wiri junction and the construction of a third main will be getting underway."

All of the projects are part of the Auckland Metro Rail Programme and once complete will deliver Auckland a resilient train infrastructure network for improved reliability of passenger train services provided by Auckland Transport and freight trains.

Earlier in the year, testing uncovered damage to more than 100km of track which required urgent upgrading.

"Our teams have put in a lot of hours and have already completed over 50 percent of the required work.

"The upgrade has been a massive task and KiwiRail has worked with Auckland Transport throughout the project to try to minimise the impact on commuters."

The network shutdown will take place from Saturday 26 December to Sunday 10 January. During that period only freight trains will operate on the tracks.

Commuters on the Western line between Fruitvale Road and Swanson will need to prepare for a longer period of disruption, with work starting earlier, on December 20, and continuing along the entire Western Line until the end of January 2021.

"We have planned the repairs on the Western line to minimise the impact when the school year begins in February."

"KiwiRail appreciates the level of cooperation and understanding from the public as this necessary work continues. The progress that will be made during the shutdown is an investment which will make the network more resilient and reduce future outages."

AT Executive General Manager Integrated Networks Mark Lambert says "Once again AT wishes to acknowledge the disruption that these works have had on our customers. We will continue to provide Rail Replacement Bus services across the network throughout the shutdown, including New Year's Eve, when many Aucklanders will be wanting to spend time with their friends and loved-ones."

For the latest information on closures visit AT.govt.nz/railclosures.

For more information on the track repair work: https://www.kiwirail.co.nz/what-we-do/projects/amp/auckland-work/

© Scoop Media

 
 
 
Business Headlines | Sci-Tech Headlines

 

CTU 2021 Work Life Survey: COVID And Bullying Hit Workplaces Hard, Huge Support For Increased Sick Leave

New data from the CTU’s annual work life survey shows a snapshot of working people’s experiences and outlook heading out of 2020 and into the new year. Concerningly 42% of respondents cite workplace bullying as an issue in their workplace - a number ... More>>

Smelter: Tiwai Deal Gives Time For Managed Transition

Today’s deal between Meridian and Rio Tinto for the Tiwai smelter to remain open another four years provides time for a managed transition for Southland. “The deal provides welcome certainty to the Southland community by protecting jobs and incomes as the region plans for the future. The Government is committed to working on a managed transition with the local community,” Grant Robertson said. More>>

ALSO:

Economy: Strong Job Ad Performance In Quarter Four

SEEK Quarterly Employment Report data shows a positive q/q performance with a 19% national growth in jobs advertised during Q4 2020, which includes October, November and December. Comparing quarter 4, 2020, with the same quarter in 2019 shows that job ad volumes are 7% lower...More>>

NIWA: 2020 - NZ’s 7th-warmest Year On Record

The nationwide average temperature for 2020, calculated using stations in NIWA’s seven-station temperature series which began in 1909, was 13.24°C (0.63°C above the 1981–2010 annual average). New Zealand’s hottest year on record remains 2016, when... More>>

Quotable Value New Zealand: Property Market Set To Cool From Sizzling To Warm In 2021

Nostradamus himself could not have predicted the strange series of events that befell our world in 2020 – nor the wild trajectory of New Zealand’s property market, which has gone from “doom and gloom” to “boom and Zoom” in record time. Even ... More>>

PriceSpy: Research Reveals How Shopping Behaviours Have Changed This Christmas

According to a new survey* from PriceSpy , almost 50 per cent of Kiwis are looking to shop locally this Christmas in light of Covid-19; The research also found consumers are changing their shopping habits, with one in seven (14 per cent) getting super-organised ... More>>