Rangitane Maritime Development Declined COVID Fast-Track Consent
An independent panel has declined resource consent to construct a public boat ramp facility at Rangitane, Kerikeri.
Far North District Council and Far North Holdings Limited applied for resource consent under the COVID-19 Recovery (Fast-track Consenting) Act 2020.
The decision comes 209 working days after the application was lodged with the Environmental Protection Authority.
The Environmental Protection Authority is not involved in the decision-making. We provide procedural advice and administrative support to the panel convenor, Judge Laurie Newhook, and the expert consenting panel he appoints.
Read the Rangitane maritime development report
Note that this application was made under the COVID-19 Recovery (Fast-track Consenting) Act 2020 and not the more recent fast-track legislation.
More about fast-track consenting under the COVID-19 Recovery (Fast-track Consenting) Act
Gordon Campbell: On How US Courts Are Helping Donald Trump Steal The Mid-Terms
Office of the Ombudsman: Ombudsman Publishes Findings On Ministry Of Education Sensitive Claims Scheme
Nelson City Council: Mayor Welcomes Auditor-General Decision Not To Prosecute Councillor
Johnnie Freeland: Ko Tātou Tātou - Climate Action In Aotearoa Begins With Relationship
Zero Waste Network Aotearoa: Container Return Scheme Bill Would Double Recycling Rates And Put Money Back In Households
Wellington City Council: Statement From The Wellington Mayoral Forum On Options For Regional Governance Reform
MUNZ: TAIC Report On Kaitaki Incident Gives Shocking Picture Of Decline Of NZ Maritime Infrastructure