Update On Tower Replacement To Restore 220 KV Transmission Line Into Northland
Transpower made good progress raising a temporary tower to restore one of its two 220 kV transmission lines (circuits) into Northland today.
However, it was not able to complete the transfer of all the conductor wire to the new tower before dark so has decided to delay the final phase of the work until Sunday morning out of concern for crew safety.
Transpower Executive General Manager Grid Delivery Mark Ryall said that with residents in Northland having sufficient supply to meet weekend demand through the 110 kV circuits, crew safety took priority.
“We had hoped to get the circuit restored today,” Mr Ryall said. “But it is complex and challenging work and we have encountered delays that mean we weren’t able to complete the work before it got dark and the weather deteriorated.
“To ensure the crews can complete the work safely the final works will be delayed until tomorrow morning.”
Mr Ryall said crews are still on track to meet Transpower’s Sunday deadline and boost capacity into Northland ahead of demand rising again from Monday morning.
“We thank Northland communities for their continued patience. I know it makes a big difference to our crews putting in the hard work on the ground.”
Bill Bennett: Fixed Voice Rules Head For Deregulation
UN Department of Global Communications: United Nations Proposes New Global Dashboard To Measure Progress Beyond GDP
Banking Ombudsman Scheme: Fraud Check Delays Well Worth The Inconvenience, Says Banking Ombudsman
Asia Pacific AML: NZ’s Financial Crime Gap - Beyond The 'Number 8 Wire' Mentality
Westpac New Zealand: Kiwi Households Adapting Despite Widespread Cost Pressure Concerns, Westpac Survey Shows
University of Auckland: Kids’ Screen Use Linked To Long-Term Deficits In Self-Control And Attention