Search

 

Cablegate: (Sbu) Embassy Ankara Construction Security Plan (Csp) -

VZCZCXYZ0000
RR RUEHWEB

DE RUEHAK #0280/01 0530515
ZNR UUUUU ZZH
R 220515Z FEB 10
FM AMEMBASSY ANKARA
TO SECSTATE WASHDC 2191

UNCLAS ANKARA 000280

SENSITIVE
SIPDIS

DEPARTMENT FOR DS/PSP/PSD AND OBO/PE/SM

E.O. 12958: N/A
TAGS: ASEC ABLD AMGT KSEO

SUBJECT: (SBU) EMBASSY ANKARA CONSTRUCTION SECURITY PLAN (CSP) -
INSTALLATION OF AIR CONDITIONING UNIT IN CAA

SENSITIVE BUT UNCLASSIFIED. PLEASE PROTECT ACCORDINGLY.

1. (U) This is an ACTION REQUEST. See paragraph 12.

2. (U) This telegram constitutes the Construction Security Plan
(CSP) for the installation of a split-pack air conditioning unit in
the Political Section suite of the CAA of Embassy Ankara. This
project requires confirmation. No action/work will be undertaken
for this project until notification of completed confirmation action
is received from the Department.

3. (SBU) Statement of Work: The subject project involves the
installation of ONE split pack air conditioning (A/C) unit in Room
216 in the Political Section suite of the CAA of Embassy Ankara.
There is no work in the core areas involved in this project. The
split-pack A/C unit will be installed on the exterior walls of the
CAA, with a four to five inch penetration made in CAA outer wall for
the refrigerant and drainage tubes of the split unit. This room
was built as an extension to the original building and has no
existing room air conditioning. The work for installation of the
split unit will be accomplished in the following manner:

A. Mounting of the exterior unit of the split-pack on the outer part
of the exterior wall adjacent to Room 216. (Three hours)
B. Mounting of the interior unit of the split-pack on the wall in
Room 216. (Three hours)
C. Boring of hole in outer wall for passage of refrigerant and
drainage tubes. Seal holes after installation. (One hour)
D. Connections of the new split pack A/C unit including electrical
and plumbing connections. (Five hours)
E. Testing of unit. (One hour)
F. Clean up and retouch. (One hour)

4. (U) Estimated start date: 26 April 2010

5. (SBU) Estimated completion date: 28 April 2010. The exterior
and interior placement and mounting of the split unit will take less
than one day. The final connection to include plumbing and
electrical connections and testing will take no more than one day,
and it will begin and be finished the same day. The estimated
completion can be earlier if approval of this CSP can be expedited.

6. (SBU) Estimated Cost: US$1,800.00. To include the A/C
equipment, materials and labor.

7. (SBU) Labor Schedule: Work will be performed by the Post's
IDIQ Air Conditioning contractor. There will be a total of four (4)
workers performing the tasks. Two craftsmen will be inside Room 216
and the other two will on the exterior of the building. Criminal
and other indices checks on the workers will be conducted prior to
start of work. Only workers yielding negative results to these will
be allowed to work. As work will take place within CAA, the
contractors performing the work will be under continuous escorts and
surveillance by appropriately cleared American employees. Two
Cleared American Escorts (CAE) will monitor the four workers to
maintain the proper escort ratio. Tools and non-electrical
materials brought in by the contractors will be inspected by ESO
before entering the work area.

8. (SBU) Procurement plan: The split units and materials for
this project will be acquired through random selection from post
stock (1 unit to be selected from 24 units available from post stock
at GSO).

9. (SBU) Secure storage: Split unit after random selection will
be taken to and maintained in the ESO secure storage, maintained
under surveillance and U.S. control.

10. (SBU) The Embassy RSO is designated as the primary Site
Security Manager (SSM) and will interface regularly with the
construction personnel and security escorts to insure compliance
with security procedures. ESO will provide technical security
assistance when needed. The RSO (SSM) and ESO will have
unrestricted access to the work site to ensure full compliance with
proper security procedures and requirements. The RSO (SSM) may
delegate the day to day operations of this project to the GSO, FM or
other security personnel, but remains responsible for the security
requirements associated with this specific project. The RSO (SSM)
may supplement, but will not lessen the provisions of this CSP as
required by local conditions and prevailing circumstances. The RSO
(SSM) will promptly notify the escort personnel of any security
inconsistencies or unauthorized work material found on the site.
The RSO (SSM), in consultation with OBO/PE/SM and DS/PSP/PSD/CAT,
may hold the project in abeyance pending resolution of any
inconsistencies or security related issues such a time as remedial
actions are taken to resolve the problem.

11. (SBU) Project documentation: The CAE personnel, acting by
and through the RSO (SSM), will maintain a log, which identifies

workers, materials, detail of work, and any anomalies. The RSO
(SSM) will immediately report any deviation from the CSP plan to
DS/PSP/PSD/CAT and OBO/PE/SM. The log will be verified daily by the
RSO (SSM) and become part of the permanent project documentation to
support any additional technical inspections.

12. (SBU) ACTION REQUESTED: Embassy Ankara requests DS/PSP/PSD
review and concur with this CSP. Work is estimated to start in late
April 2010 or earlier if approval of this CSP is received. Points
of contact for this project are RSO James Combs (x7014), ESO Elbert
Calpo (x7030), AGSO Sarah Borenstein (x7381), FM Sergio Tristan
(x7323), MGT Martina Polt (x7444). Embassy Ankara IVG prefix code
is 295 and telephone number is (011) (90) (312) 455-5555.

13. RSO has cleared this message.
JEFFREY

© Scoop Media

 
 
 
World Headlines

 


Palestinian Ministry of Health: Developments In The Health Situation During The Israeli Aggression On The Cities & Governorates Of The Gaza Strip
For the second day in a row, the Israeli aggression against the Gaza Strip continues by targeting overcrowded residential areas and neighborhoods, as the death toll rose to 13 citizens, including a 5-year-old girl and a 23-year-old woman... More>>


UN: Horn Of Africa Faces Most ‘Catastrophic’ Food Insecurity In Decades, Warns WHO

The World Health Organization (WHO) warned on Tuesday that the Greater Horn of Africa is experiencing one of the worst famines of the last 70 years... More>>

FAO: Warns 90 Per Cent Of Earth’s Topsoil At Risk By 2050
A full 90 per cent of the Earth’s precious topsoil is likely to be at risk by 2050, according to the UN Food and Agriculture Organization, FAO...
More>>


Somalia: ‘We Cannot Wait For Famine To Be Declared; We Must Act Now’
Rising acute food insecurity in Somalia has caused more than 900,000 people to flee their homes in search of humanitarian assistance since January last year, the Food and Agriculture Organization (FAO) has warned... More>>

UN: American West Faces Water And Power Shortages Due To Climate Crisis
Two of the largest reservoirs in the United States are at dangerously low levels due to the climate crisis and overconsumption of water, which could affect water and electricity supply for millions in six western states and Mexico, the UN Environment Programme (UNEP) warned on Tuesday... More>>



Singapore: UN Experts Call For Immediate Moratorium On Executions For Drug Offences

UN experts* today condemned the execution of Nazeri Bin Lajim, a 64-year-old Malay Singaporean national convicted of drug offenses and urged the Government of Singapore to halt plans to execute individuals on death row for drug related charges... More>>