Major Mangamuka electricity repair job completed
Major Mangamuka electricity repair job completed
Single high-voltage line supplying Kaitaia
and districts no longer under threat
Top Energy has completed successfully a $550,000 major engineering and repair project in the Mangamukas, averting the risk of a tower collapse that could potentially have disrupted power supplies to Kaitaia and surrounding districts for weeks.
Heavy rain in the Mangamukas shortly before Christmas caused a 100m-long land-slip in rough terrain which dislodged and severely damaged a lattice tower carrying the only high-voltage line supplying electricity to the town.
A replacement structure was built during February and March and on Sunday the final conductors (electricity lines) were switched from the failing tower to the new one.
ends
Gordon Campbell: On The Political Panic Over Immigration
Internal Affairs: Citizenship Test For Citizenship By Grant Applicants From Late 2027
Dayenu: Condemning Use Of Government Funding For Extremist Report On Antisemitism
PSA: Councils Must Work With Unions And Communities In Fast-Track Reform
Tauranga City Council: Mauao Restoration Work Has Begun
Horizon Research: New Poll Finds High Concern About Fuel Situation
Tiaki Wai: Over 1,150 People Give Feedback On Tiaki Wai Water Services Strategy